Asheville City Council recorded 14 votes at its regular meeting on April 8, 2025; 1 drew at least one no vote. Most items fell under Boards & Appointments, Transportation and Zoning & Land Use.
Met: 5 pm–7:31 pm. Voting: Bo Hess, Esther E. Manheimer, S. Antanette Mosley, Kim Roney, Sheneika Smith, Sage Turner, Maggie Ullman.
Votes 14 recorded · 4 substantive · 1 split
Item C · RES 25-78 · Transportation · Resolution · consent agenda
Contract with Appalachian Sitework Inc. for the Patton Avenue Sidewalk Improvements project
Passed7–0 · Moved by Sheneika Smith, seconded by S. Antanette Mosley
All members present voted yes.
Recommendations
Council’s vote matched the city staff recommendation.
City staff: Approve — Appalachian Sitework Inc. was deemed the lowest responsive, responsible bidder, and are therefore being recommended for award.
Key facts
$743,339.07contract with Appalachian Sitework Inc.
$74,333.91the Contingency amount of $74,333.91 (10%)
Patton Avenue in West Asheville, from its intersection with Louisiana Avenue to its intersection with Druid Driveaddress
Appalachian Sitework Inc.contractor or recipient
approved through a 2016 Bond Referendumfunding source
Construction Anticipated Start Date: June 2025; Construction Anticipated End Date: April 2026term
Description in the minutes
Action Requested:
Adoption of a resolution authorizing the City Manager to enter into a contract with Appalachian Sitework Inc. in the amount of $743,339.07, for Patton Ave. Sidewalk Improvements, and further, authorizing the City Manager to execute any change orders that may arise during the project up to the Contingency amount of $74,333.91 (10%).
Background:
Funding for Sidewalk, Pedestrian and Safety Improvements along Patton Ave. was approved through a 2016 Bond Referendum.
The Patton Ave. Sidewalk Improvements project includes the installation of approx. 0.45 miles of sidewalk, as well as the installation of curb-and-gutter, crosswalks, and bus pads, along Patton Avenue in West Asheville, from its intersection with Louisiana Avenue to its intersection with Druid Drive. Project page
This project was initially advertised for Bid in February 2023 (#298-PattonSidewalk-FY23). Not enough bids were received and the project did not move forward.
This project was then rebid in March 2023 (#298-RebidPatton-FY23), but not enough bids were received and the project did not move forward.
This project was then advertised for bid again on 02/06/2025, and three (3) bids were received from responsive, responsible bidders on 02/27/2025. The Bidders and Bids are listed below.
Appalachian Sitework Inc. was deemed the lowest responsive, responsible bidder, and are therefore being recommended for award.
Construction Anticipated Start Date: June 2025; Construction Anticipated End Date: April 2026.
Curb and Gutter work may only be performed at night between the hours of 7 PM and 6 AM.
Vendor Outreach Efforts:
Staff performed outreach to minority and women owned businesses through solicitation processes that included emailing select MWBE vendors after bid issue, posting on the State’s Interactive Purchasing System, and conducting a Pre-Bid meeting with Marcus Kirkman, wherein ABI policy was clearly explained to attendees.
The recommended Bidder will be utilizing a minority-owned business for Traffic Control, with this participation representing 3.6% ($27,000) of the Total Bid.
Council Goal(s):
Transportation and Accessibility
Connected and Engaged Community
Thriving Local Economy
Committee(s):
None
Pro(s):
This project directly achieves Council goals and resolutions.
It will provide a safe, accessible pedestrian route where it is sorely needed: in an area with high vehicular volume, a history of vehicular accidents, where pedestrians have to cross busy streets, driveways, and walk inches from Patton Avenue to access bus-stops and local businesses.
The need for a pedestrian route here is made even more evident by a well-worn “desire path”, engrained in the mud and turf, in the exact area where sidewalk will be installed.
Con(s):
During Construction, traffic flow will be impacted along Patton Ave, as well as traffic flow in and out of parking lots that serve commercial businesses.
The impact is mitigated through timing restrictions for certain construction activities (for example, curb and gutter work can only be performed at night), through the installation of https://www.ashevillenc.gov/projects/west-patton-avenue-sidewalk/ traffic control devices, and by providing safe, accessible pedestrian access routes through the construction zone at all times.
Fiscal Impact:
Funding for this contract is already included in the adopted Capital Improvement Program (CIP).
Staff: Walter Ear, Capital Projects Director; Jill Weissman, Project Manager.
Copied word for word from the minutes (“…” marks words left out).
0 spoke in favor · 0 spoke against · 1 stance not recorded
Not recordedPatrick Conant — Patrick Conant spoke about Council’s duty to participate in the appointment process, and felt Council should take their time to fully review all applications and appoint the strongest possible group.
Mayor Manheimer asked for public comments on any item on the Consent Agenda, but received none.
OpposesToday, she will give gratitude to Vice Mayor [Mosley] who will represent Council in the non-voting seat, to the 50 applicants who were willing to serve in this new role, and to the 20 nominees who are anticipated to carry this work forward. … Additionally, she has heard from more than one ADA board member that the board did not have input on the ADID selections … improvement district is not the right tool for the serious issues we face, she will not be voting to advance the board today
ConcernCouncilwoman Roney said that the nomination of the ADID board was originally under unfinished business. After Council’s agenda briefing, it was moved to the consent agenda.
The minutes record no remarks on this item from Bo Hess, Esther E. Manheimer, S. Antanette Mosley, Sheneika Smith, Sage Turner and Maggie Ullman.
Key facts
At the request of Councilwoman Roney, Consent Agenda Item “E” was removed from the Consent Agenda for discussion and/or an individual vote.
From the staff report
Adoption of a motion approving the appointment of the proposed slate of members for the Asheville Downtown Improvement District board (the entity operating the Downtown Business Improvement District).
Fiscal impact
This action does not have a fiscal impact on the City.
Staff’s stated reasons
Establishment of the steering committee/board will support the timely rollout of services of the Downtown Business Improvement District.
Before it reached Council
Downtown Commission, August 30, 2024 — Board make-up was not explicitly considered for a vote by either of these bodies.
Planning and Economic Development Committee of City Council, September 9, 2024 — Board make-up was not explicitly considered for a vote by either of these bodies.
Resolution authorizing City staff to submit (CDBG-DR action plan) to HUD for review and approval
Passed7–0 · Moved by Sage Turner, seconded by Kim Roney
All members present voted yes.
4 spoke · 4 council remarks
Recommendations
Council’s vote matched the city staff recommendation.
City staff: Approve — Staff is seeking City Council's authorization to submit the CDBG-DR Action Plan to HUD for approval.
Public comment on this item
4 spoke in favor · 0 spoke against
Four individuals spoke to Council in support of the CDBG-DR Action Plan and urged Council to prioritize climate resilience. The minutes give counts but do not name the speakers.
What council members said 4 remarks from 4 members
Concern[Councilwoman Roney] didn’t see it explicitly named in our plan but she hears the threads of it in the input. Our plan is kind of vague because we need to move quickly and we have very specific goals. … What she heard was please don’t let the plan sit on a shelf.
QuestionIn response to Councilwoman Turner, [James Shelton] explained that using the funds for capital projects is a best practice as it’s very difficult to make investments in businesses that are strictly for operational costs. Giving a grant though HUD programs can be very stringent for disaster recovery investment.
The minutes record no remarks on this item from Esther E. Manheimer, S. Antanette Mosley and Maggie Ullman.
Key facts
$225.01 milliondirect allocation of Community Development Block Grant - Disaster Recovery (CDBG-DR) funds in the amount of $225,010,000
U.S. Dept. of Housing & Urban Developmentcontractor or recipient
CDBG-DR funds on a reimbursement basisfunding source
Presented by James Shelton, Community Development Division Manager.
From the staff report
Adoption of a resolution to authorize staff to submit the Community Development Block Grant - Disaster Recovery (CDBG-DR) Action Plan to the US Department of Housing and Urban Development for review and approval
$225.01 millionin the amount of
Special Revenue Fundfunding source
Fiscal impact
City will receive $225,010,000 in CDBG-DR funds on a reimbursement basis. Funding is already budgeted in the Special Revenue Fund.
Staff’s stated reasons
By submitting the Action Plan to HUD, the city can begin the process of implementing the programs that are proposed within the plan once HUD approves.
Approval at this time will allow the city to submit the Action Plan prior to HUD’s April 21st, 2025 deadline.
Staff: Nikki Reid, Community & Economic Development Director; James Shelton, Community Development Division Manager.
Description in the minutes
Community Development Division Manager James Shelton said that this is the consideration of a resolution authorizing the City staff to submit the Community Development Block Grant
Disaster Recovery Action Plan to the U.S. Dept. of Housing & Urban Development for review and approval.
Background:
The US Department of Housing and Urban Development (HUD) has provided the City of Asheville with a direct allocation of Community Development Block Grant
Disaster Recovery (CDBG-DR) funds in the amount of $225,010,000 to address unmet needs resulting from the effects of Tropical Storm Helene.
To receive the CDBG-DR funds, the City must submit an Action Plan to HUD that details what our community’s ongoing unmet needs are as a result of the disaster and what programs and activities we intend to fund to address those needs.
The City has engaged in an extensive data analysis and community engagement process to identify those unmet needs.
Based upon the identified needs, as well as what the community and council have identified as priorities for recovery, a Draft Action Plan was developed and posted for public comment on March 4th.
Public comment was received for 30 days online, via email, and at 3 in-person public feedback sessions.
All comments were responded to and attached to the plan, changes were made to the Action Plan according to public comment (in alignment with needs, funding availability, and eligibility within the program) and noted as such in the plan.
City Council must now authorize staff to submit the Action Plan to HUD for review and approval.
Committee(s):
None. Council committees are suspended following Tropical Storm Helene.
Pro(s):
By submitting the Action Plan to HUD, the city can begin the process of implementing the programs that are proposed within the plan once HUD approves.
Approval at this time will allow the city to submit the Action Plan prior to HUD’s April 21st, 2025 deadline.
Con(s):
None
Fiscal Impact:
City will receive $225,010,000 in CDBG-DR funds on a reimbursement basis. Funding is already budgeted in the Special Revenue Fund. Mr. Shelton outlined the following key takeaways from his presentation: (1) Since Helene, the City of Asheville has worked to secure resources from FEMA, the State of North Carolina, and others for the long-term recovery. On January 16, 2025 HUD allocated $225,010,000 in CDBG-DR funds to the City and directed the City to develop a CDBG-DR Action Plan; (2) The CDBG-DR Action Plan estimates the City’s unmet needs and describes how the City intends to use CDBG-DR funding to address those unmet needs. A robust community engagement process informed the plan: (a) Over 325 comments were received throughout the process. Each comment has been responded to and included as an appendix in the plan; and (b) The final allocations, as well as programmatic language, were adjusted to reflect these comments and the feedback received will further inform the implementation of the CDBG-DR Action Plan; (3) At this time, staff is seeking City Council’s authorization to submit the CDBG-DR Action Plan to HUD for approval. (a) Best practice is to be intentional and strategic about the programs that we pursue, with a focus on early wins, planning, and long-term resilience. The Plan can be amended as needed; and (b) This Plan will work in concert with the State of NC’s CDBG-DR Action Plan for $1.4B – specifically, recognizing their focus on housing programs and our need to be responsive to economic and infrastructure resilience; and (4) Once the Plan is submitted for approval, we’ll then begin planning our implementation for activating these funds into our community for recovery. He then reviewed the CDBG-DR process overview. The City’s Helene recovery priorities survey’s takeaways shared in February are (1) Strengthen infrastructure
Focus on water system improvements and climate-adaptive rebuilding; (2) Expand housing solutions
Increase emergency shelter, rent assistance, and affordable housing development; (3) Support economic recovery
Focus on business assistance and workforce stabilization; (4) Enhance food security
Ensure access to essential supplies during crises; and (5) Maintain sustainability focus
Integrate climate resilience into recovery planning. He then explained the CDBG-DR community engagement sessions (1) Six input sessions throughout February prior to plan development (a) 623 direct comments on our community’s ongoing unmet needs; (b) Key things we heard around each of the CDBG-DR categories: (i) Infrastructure improvements: Parks, water system resiliency, roads, enhancing public spaces; (ii) Economic revitalization: Business and economic diversification and support for small businesses; and (iii) Affordable housing: Need to restore and build new housing units; (2) Draft CDBG-DR Action Plan published on March 4th (a) Public comment collected via publicinput.com/cdbg-dr or email for 30 days (March 4
April 3); and (b) 3 public feedback sessions held in March on Housing, Economic Revitalization; and Infrastructure; and (3) All comments responded to and attached to final Plan
Any changes to Plan as a result of comments are noted as such. He gave project stats for the public comment period, along with a sample of public comment participants. Using charts, he explained the alignment with State of North Carolina CDBG-DR Program allocations. Then, using charts, he showed the CDBG-DR Program recommendations and public feedback highlights. The following are proposed allocations in the final plan connection between unmet needs and allocations are in the following program areas: Housing
$31,000,000; Infrastructure
$125,000,000; Economic Revitalization
$52,000,000; Public Services
$2,000,000, Planning
$3,759,500; and administration
$11,250,500. Total $225,010,000. He then reviewed the housing public feedback highlights, along with recommendations as follows: (1) Gap funding for the construction and preservation/rehabilitation of affordable multifamily projects
Multi-family projects best positioned to reach deeper levels of affordability; (2) State R&R Program: City will pay for hard costs and State will cover administration cost and tim; (3) Projects in City limits are eligible to apply for other State funding programs; (4) Lowered the minimum award to $500,000, and has added language to the Affordable Multi-Family Housing Construction Program to allow for multiple Notices of Funding Opportunities (NOFOs) to be released, which may have different minimum award criteria and allow for smaller unit developments; and (5) Amount increased by $2M as a result of public comment. Changes also made to minimum award amounts and partner selection criteria for deeper affordability. He then reviewed the infrastructure public feedback highlights, along with the recommendations as follows: (1) Water System Improvements
such as floodproofing and infrastructure hardening to prevent service interruptions; (2) Stormwater management
may include constructing or rehabilitating flood control structures and implementing green infrastructure; (4) Parks, recreation, and arts and cultural facility improvement to increase community-building within the city; (4) Affordable housing infrastructure
potential upgrades to water, sewer, and energy systems, as well as site improvements like lighting, sidewalks, and transit access; (5) Commercial district revitalization such as streetscape enhancements, broadband expansion, and public facility upgrades; and (6) Emergency sheltering development & construction. He then reviewed the economic revitalization public feedback highlights, along with the recommendations as follows: (1) The Revitalization of Flooded Commercial Districts Program will provide comprehensive funding to address the recovery of Asheville’s flooded commercial districts. Funding includes, but is not limited to, site development and improvements, improvements to public spaces, facility improvements, flood-proofing, and equipment investments; (2) The Small Business Support Program provides grants and/or loan funds to local small businesses or small business support organizations to target job creation, job retention, and business diversification within the City; (3) The Workforce Development Program addresses an unmet need for skilled labor and specialized training to benefit Asheville’s recovery from Helene and rebuilding efforts. This Program may provide funding for construction trade programs, on-the-job training, and other technical skills; and (4) Amount increased by $2M to respond to public comment. Regarding public services, (1) Provides funds to public or non-profit organizations to reduce and prevent homelessness in the City
Activities may include rapid-rehousing initiatives and housing counseling services; and (2) Also provides funds to workforce development support organizations to help address barriers to employment within the City
Activities may include funding for paid training programs, transportation and/or child care stipends while receiving training, and other wraparound services. He then reviewed the planning public feedback highlights, along with the recommendations as follows: (1) the updates to the existing plans may include, but are not limited to: an update to the Wilma Dykeman Riverway Master Plan; updates to the Affordable Housing Plan; a Strategic Plan with recommended updates to the Unified Development Ordinance; neighborhood plans; public works plans, multi-modal transportation planning; and (2) the long-term recovery planning may include: area-specific plans for areas with concentrated damage; infrastructure recovery plans; community connectivity and resiliency plans; housing recovery and resiliency plans; supporting the CoC with emergency shelter planning; and economic recovery and resiliency plans. Each amount increased by $500,000 in response to public comment. Regarding mitigation, (1) Strengthening flood resilience and stormwater management
Reinforcing critical infrastructure, enhancing water resiliency, modernizing stormwater infrastructure, etc.; (3) Enhancing housing resilience and community adaptation
Prioritize historically underserved communities with hazard mitigation efforts; and (4) Supporting economic recovery and risk diversification
Diversifying local economy, strengthening financial recovery programs, prioritizing flood mitigation in commercial districts, etc. Mitigation efforts will be woven into implementation. He then explained how the City Action Plan maintains compliance with HUD guidance. Councilwoman Roney said that it’s unsurprising to her that food security was a top priority for our neighbors. Back in 2021 at the City Council retreat, Councilwoman Smith joined her in pushing to add neighborhood resiliency in our City Council goals and Councilwoman Smith said something about resilience hubs. She wasn’t sure what that was. After researching that term, she found resiliency hubs are places in your neighborhood
it can be a spot on your street, the library, a place where you share food and resources
where we share information. It could look like community centers, faith community centers that have solar with back-up batteries, so that we can have emergency response at the neighborhood level. She didn’t see it explicitly named in our plan but she hears the threads of it in the input. Our plan is kind of vague because we need to move quickly and we have very specific goals. The resilience hub was what people were doing
they were filling the gap until the government could respond. Also. $1.1 Billion in needs assessment is a hard number to wrap your mind around, but it’s not enough yet it seems like a lot. Among the plans that we have in our community is the climate justice initiative plan and it shows our vulnerability to not only flooding and wildfires, but also landslides. What she heard was please don’t let the plan sit on a shelf. Mr. Shelton responded to Councilman Hess when he asked about child care assistance; and Councilwoman Smith when she asked about assistance for the Gig community
buskers, and people who do not have brick and mortar businesses. In response to Councilwoman Turner, Mr. Shelton explained that using the funds for capital projects is a best practice as it’s very difficult to make investments in businesses that are strictly for operational costs. Giving a grant though HUD programs can be very stringent for disaster recovery investment. Four individuals spoke to Council in support of the CDBG-DR Action Plan and urged Council to prioritize climate resilience. Mayor Manheimer said that members of Council have previously received a copy of the resolution and it would not be read.
Copied word for word from the minutes (“…” marks words left out).
Ordinance adopting the Fiscal Year 2025-26 fees and charges manual
Passed7–0 · Moved by Sage Turner, seconded by Maggie Ullman
All members present voted yes.
Recommendations
Council’s vote matched the city staff recommendation.
City staff: Approve — Staff recommendations for FY 2025-26 include: (a) Continuation of the planned water fee increases (year 2 of the 3-year phase in); and (b) An initiation of a fee to rent the Memorial Field Track.
Key facts
$1,500expected to lead to approx. $1,500 in additional revenue
$24.72Residential - 5/8” (8 CCF) $4.12 $24.72
major revenue source for Enterprise Fundsfunding source
Effective July 1, 2025term
When Mayor Manheimer asked for public comments, none were received.
Presented by Lindsay Spangler, Budget Manager.
From the staff report
Adoption of an ordinance establishing the fees and charges for FY 2025-26.
$2.4 millionadditional revenue
$15per hour
Fiscal impact
Impacts for each recommended change are shown in Attachment A.
Staff’s stated reasons
Provides for cost recovery from those that directly utilize or benefit from the service where appropriate, reducing the financial burden of City services on taxpayers.
Provides additional revenue to support major infrastructure projects in the Water Enterprise Fund.
Budget Manager Lindsay Spangler said that this is the consideration of adoption of an ordinance establishing the fees and charges for FY 2025-26.
Background:
Staff reviews fees and charges as part of the budget process each year and brings forward recommendations for adjustments early in the process.
Fees and charges represent a small portion of General Fund revenues but are the major revenue source for Enterprise Funds.
Fees and charges made up 31% of total budgeted revenue in the current fiscal year.
As discussed with City Council at the March 11 Budget Work Session, staff is proposing fee adjustments in Water that represent year two of the three-year rate plan phase-in that began in the current fiscal year.
Outside of Water, staff is proposing only one other fee adjustment, which is the adoption of a rental fee for the Memorial Stadium Track.
All other fees will remain unchanged in FY 2025-26.
More detailed and specific information regarding the fee adjustment was provided as part of this report.
If approved, fee adjustments will become effective July 1, 2025.
Proposed changes are based on impacts to revenues, customers, and service provision. Typical household impact of the Water fee changes proposed for FY 2025-26 is below: Bimonthly Usage Bi-Monthly Bill Increase FY26 Annual Increase Residential
5/8” (8 CCF) $4.12 $24.72 Commercial
5/8” (84 CCF) $32.18 $193.08 Commercial
1” (120 CCF) $46.81 $280.86 Manufacturing
4” (4,992 CCF) $2,698.62 $16,191.72 Manufacturing
8” (26,306 CCF) $16,903.15 $101,418.90 Wholesale
8” (18,120 CCF) $9,852.03 $59,112.18
Pro(s):
Provides for cost recovery from those that directly utilize or benefit from the service where appropriate, reducing the financial burden of City services on taxpayers.
Provides additional revenue to support major infrastructure projects in the Water Enterprise Fund.
Allows staff to begin communicating fee changes to citizens, customers, and stakeholders so they are aware of changes that will be implemented on July 1, 2025.
Con(s):
An increase in the cost of city Water services.
Fiscal Impact:
Impacts for each recommended change are shown in the document provided. Ms. Spangler outlined the following key takeaways from her presentation as follows: (1) Staff reviews fees and charges as part of the budget process each year and brings forward recommendations for adjustments early in the process; (2) Fees and charges represent a small portion of General Fund revenues but are the major revenue source for Enterprise Funds; (3) Due to the financial impact of Tropical Storm Helene on service users, staff recommends to keep fees and charges changes minimal; and (4) Staff recommendations for FY 2025-26 include: (a) Continuation of the planned water fee increases (year 2 of the 3-year phase in); and (b) An initiation of a fee to rent the Memorial Field Track. Ms. Spangler then showed a chart of the FY 2024-25 General Fund revenues and the FY 2024-25 Enterprise Fund revenues. Regarding the water cost of service study, (1) A Water Cost of Service Study was completed in late 2023 that determined the cost of service by functional area, assessed the rate structure, and made recommendations for multi-year rate adjustments; (2) The results of the Study were discussed with the Policy, Finance, & HR Committee in multiple meetings during last year’s budget process; (3) Staff recommended a three-year phase-in approach to the proposed rate adjustments as the most efficient, effective and equitable approach for our customers since it will eliminate inequity among customer classes sooner, establish needed funding for the capital program, and preserve the City’s debt ratings; (4) City Council adopted year one of the three-year rate adjustments in March 2024 with an effective date of July 1, 2024; (5) Financial Sufficiency
Ongoing rate adjustments are needed to fund a 5-year capital program initially estimated at $239 million prior to Helene; and (6) Equity / Cost of Service (a) Study found the residential class was subsidizing other customer classes; specifically commercial/manufacturing and wholesale; (b) Therefore, commercial/manufacturing and wholesale customer classes will see higher rate increases relative to other classes; and (c) A 3-year phase-in of the rate adjustments was recommended and shared with system customers during last year’s budget process. The FY 2025 year-one rate adjustment accomplishments are as follows: (1) Issued $26.9M in Water Revenue Bonds in September for the meter replacement project; (2) Increased pay-go capital funding by $2.7M in FY25 to continue infrastructure replacement projects; (3) Added a new Project Manager/Engineer position to design and oversee capital projects; (4) Added a Water Communication Specialist (PIO); and (6) Added four new positions for a South District Crew to improve response time for emergency water main breaks and provide better customer service. The importance of continued rate adjustments are (1) Additional debt issuances are upcoming for projects that are either already underway or planned: (a) $12.5M
Water Treatment Plant (WTP) Rehab Project; (b) $75M
WTP treatment enhancements; and (c) $40M
Mills River Expansion Phase III; (2) Ratings Agencies use metrics such as debt service coverage and reserves to determine ratings for future bonds
S&P has put Water on a “credit watch with negative implications” pending outcome of rate discussions; and (3) The community rated Strengthening Infrastructure as a top concern in the Helene Recovery Priorities survey. She then reviewed charts of a base rate comparison, the typical customer bill impacts, and the typical user impact. Regarding the Memorial Stadium track fee, (1) Due to the completion of the new track, the Parks and Recreation Department requests to set a fee of $15/hour to rent the track
This is expected to lead to approx. $1,500 in additional revenue; and (2) This fee allows Parks to remain consistent with the way it manages its other resources. Charging a fee will allow them to better manage the utilization of their facility. When Mayor Manheimer asked for public comments, none were received. Mayor Manheimer said that members of Council have previously received a copy of the ordinance and it would not be read.
Copied word for word from the minutes (“…” marks words left out).
Item B · RES 25-77 · Public Safety · Resolution · consent agenda
Funding agreement with North Carolina Emergency Management for state disaster assistance after Tropical Storm Helene
Passed7–0 · Moved by Sheneika Smith, seconded by S. Antanette Mosley
All members present voted yes.
Key facts
State of North Carolina, Division of Emergency Managementcontractor or recipient
Disaster Assistance funds for FEMA Public Assistance and other FEMA programsfunding source
Description in the minutes
Action Requested:
Adoption of resolution to enter into a funding agreement with the State of North Carolina, Division of Emergency Management for all disaster assistance funds provided by or through the State in response to the disaster, Tropical Storm Helene.
Background:
The Major Disaster Declaration made by the President of the United States numbered FEMA DR-4827-NC, Tropical Storm Helene, will provide disaster assistance funds to qualifying applicants.
Disaster Assistance funds for FEMA Public Assistance and other FEMA programs once obligated are passed to the State of North Carolina, Division of Emergency Management for disbursement to local governments.
While expedited funding has already been received, this funding agreement is required to ensure timely processing of Request for Reimbursements for FEMA related projects.
This funding agreement is required to receive both Federal and State portions of disaster assistance.
Vendor Outreach Efforts:
N/A Council Goal:
Financially Resilient City Committee:
No prior Committee approval. Pro:
Required agreement to continue to receive disaster assistance funding related to Tropical Storm Helene.
Con(s):
None
Fiscal Impact:
Agreement is a required step in continuing to receive disaster assistance funding both on a state and federal level. This includes FEMA funding already approved by the council.
Staff: Becki Ogles, Assistant Finance Director; Tony McDowell, Finance Director.
Copied word for word from the minutes (“…” marks words left out).
Monthly municipal property tax refunds or releases per N.C. statute
Passed7–0 · Moved by Sheneika Smith, seconded by S. Antanette Mosley
All members present voted yes.
Description in the minutes
Action Requested:
Adoption of City of Asheville property tax refunds and releases for the month of February 2025..
Background:
Buncombe County currently bills and collects City property taxes
At the August 22, 2023, meeting, City Council approved an addendum to the existing tax collection agreement with Buncombe County to ensure that it fully conforms to the provisions of Chapter 105 of the North Carolina General Statutes, entitled The Revenue Act.
As part of that compliance, the City Council must, on a monthly basis, approve all property tax releases and refunds that have been approved by the Buncombe County Board of Commissioners.
City of Asheville refunds and releases for February 2025 are included in the document.
Council Goal(s):
A Financially Resilient City
Pro(s):
Ensures compliance with provisions of Chapter 105 of the North Carolina General Statutes, entitled The Revenue Act.
Con(s):
None
Fiscal Impact:
None. Suggested Motion:
Motion to adopt City of Asheville property tax refunds and releases for the month of February 2025
Staff: Tony McDowell, Finance Director.
Copied word for word from the minutes (“…” marks words left out).
Motion amending the 2025-26 Council meeting agenda to cancel April 17 agenda briefing worksession and cancel April 22 formal meeting
Passed7–0 · Moved by Sheneika Smith, seconded by S. Antanette Mosley
All members present voted yes.
Description in the minutes
(1) CANCEL THE APRIL 17, 2025, AGENDA BRIEFING WORKESSION; AND (2) CANCEL THE THE CITY COUNCIL FORMAL MEETING ON APRIL 22, 2025 Mayor Manheimer asked for public comments on any item on the Consent Agenda, but received none. Mayor Manheimer said that members of Council have been previously furnished with a copy of the resolutions and ordinances on the Consent Agenda and they would not be read.
Copied word for word from the minutes (“…” marks words left out).
Item IV-A · RES 25-79 · Zoning & Land Use · Public hearing
Public hearing to close an unopened right-of-way (Brevard Rd parcels)
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
1 council remark
Recommendations
Technical Review Committee: Approve, unanimous, December 2, 2024
Public hearing 5:52 pm–5:52 pm · advertised Mar 14, 2025 and Mar 21, 2025 and Mar 28, 2025 and Apr 4, 2025
No one from the public spoke.
Due to the temporary suspension of boards and commissions, the Multimodal Transportation Commission did not review the request. … when no one spoke, she closed the public hearing at 5:52 p.m.
QuestionIn response to Councilwoman Ullman, [Jessica Morriss] said that the Technical Review Committee reviews these closings, with the lens on transportation, utilities, etc.
The minutes record no remarks on this item from Bo Hess, Esther E. Manheimer, S. Antanette Mosley, Kim Roney, Sheneika Smith and Sage Turner.
Key facts
unopened right-of-way (ROW) connected to Morningside Drive between Coventry Circle and Brevard Roadaddress
Chris Johnson, Finance and Operations Manager for Nicholson & Sun on behalf of the Owner, Kevin Hole LLCapplicant
No fiscal impactfunding source
Presented by Jessica Morriss, Assistant Transportation Director.
From the staff report
Adoption of a resolution to permanently close a portion of an unopened right-of-way connected to Morningside Dr, located between 99999 Coventry Cir (963810210800000) and 99999 Brevard Rd (963810327200000).
Chris Johnson, Finance and Operations Manager for Nicholson & Sun on behalf of the Owner, Kevin Hole LLC has submitted an application requesting to permanently close approximately 208' of unopened alley ROWasked for this item
Fiscal impact
This action requires no (additional) City resources and has no fiscal impact.
Staff’s stated reasons
There are no utility conflicts, nor any transportation connectivity opportunities associated with this unopened right-of-way.
Assistant Transportation Director Jessica Morriss said that this is the consideration of a resolution to permanently close an unopened right-of-way (ROW) connected to Morningside Drive between Coventry Circle and Brevard Road. This public hearing was advertised on March 14, 21, 28 and April 4, 2025.
Background:
North Carolina General Statute § 160A-299 grants cities the authority to permanently close streets and alleys. The statute requires City Council to consider whether the closure of the Right-of-Way has a negative impact to the public interest and whether the closure would impede access to parcels, utilities, and other public infrastructure.
Chris Johnson, Finance and Operations Manager for Nicholson & Sun on behalf of the Owner, Kevin Hole LLC has submitted an application requesting to permanently close approximately 208' of unopened alley ROW on the southernmost portion of the alley accessed from Morningside Drive.
There are no utility conflicts, nor any transportation connectivity opportunities associated with this unopened right-of-way.
Committee(s):
Technical Review Committee, December 2, 2024, unanimously recommended approval.
Multimodal Transportation Commission (MMTC)
Due to the temporary suspension of boards and commissions, the MMTC did not review the request. However, MMTC review is not legally required and the applicant has requested to move forward.
Pro(s):
There are no utility conflicts, nor any transportation connectivity opportunities associated with this unopened right-of-way.
Con(s):
None.
Fiscal Impact:
This action requires no (additional) City resources and has no fiscal impact. Ms. Morriss said (1) Nicholson & Sun, LLC has petitioned for this closure on behalf of the property owner, Kevin Hole, who owns the properties at 99999 Coventry Cir (963810210800000) and 99999 Brevard Rd (963810327200000); and (2) The unopened right-of-way connects to Morningside Drive, however it is only the southernmost portion of the ROW (~208 feet) that the applicant seeks to close. She used a map, plat and pictures to show the closing. She said the Technical Review Committee (TRC) met on December 2, 2024, recommendation was to approve the closure. Due to the temporary suspension of boards and commissions, the Multimodal Transportation Commission did not review the request. However, MMTC review is not legally required and the applicant has requested to move forward. In response to Councilwoman Ullman, Ms. Morriss said that the Technical Review Committee reviews these closings, with the lens on transportation, utilities, etc. Mayor Manheimer opened the public hearing at 5:52 p..m., and when no one spoke, she closed the public hearing at 5:52 p.m. Mayor Manheimer said that members of Council have previously received a copy of the resolution and it would not be read.
Copied word for word from the minutes (“…” marks words left out).
Passed7–0 · Moved by Sage Turner, seconded by Bo Hess
All members present voted yes.
Recommendations
Council’s vote matched the city staff recommendation.
City staff: Approve — The Chair and the staff liaison recommended to appoint James Wornall as the alternate member.
Boards & Commissions Committee: Approve
Key facts
James Wornall Jr.applicant
an unexpired term until January 21, 2027term
Description in the minutes
Vice-Mayor Mosley, Chair of the Boards & Commissions Committee, said that this is the consideration of appointing alternate members to the Board of Adjustment. The term of John Kledis (alternate) resigned, thus leaving an unexpired term until January 21, 2027. The following individuals applied for the vacancies: Joseph Fitzgerald and James Wornall Jr. The Chair and the staff liaison recommended to appoint James Wornall as the alternate member.
Copied word for word from the minutes (“…” marks words left out).
Resolution reappointing Carol Goins to the Civil Service Board
Passed7–0 · Moved by Bo Hess, seconded by Kim Roney
All members present voted yes.
Recommendations
Boards & Commissions Committee: Approve
Key facts
additional two-year term, term to expire May 21, 2027 … one-year term, term to expire May 21, 2026term
Description in the minutes
Vice-Mayor Mosley, Chair of the Boards & Commissions Committee, said that this is the consideration of appointing members to the Civil Service Board.. The terms of Carol Goins (current Chair) and Carter Webb expire on May 21, 2025. In addition, City Council must appoint a Chair. Carol Goins and Richard Deavereaux are interested in the seat of Chair. The following individual applied for the vacancy: James Wornall Jr. The Chair recommended reappointment of Carter Webb.
Copied word for word from the minutes (“…” marks words left out).
Resolution reappointing Carter Webb to the Civil Service Board
Passed7–0 · Moved by Sage Turner, seconded by Sheneika Smith
All members present voted yes.
Description in the minutes
Vice-Mayor Mosley, Chair of the Boards & Commissions Committee, said that this is the consideration of appointing members to the Civil Service Board.. The terms of Carol Goins (current Chair) and Carter Webb expire on May 21, 2025. In addition, City Council must appoint a Chair. Carol Goins and Richard Deavereaux are interested in the seat of Chair. The following individual applied for the vacancy: James Wornall Jr. The Chair recommended reappointment of Carter Webb.
Copied word for word from the minutes (“…” marks words left out).
Resolution reappointing Carol Goins as Chair of the Civil Service Board
Passed7–0 · Moved by Sheneika Smith, seconded by Bo Hess
All members present voted yes.
Description in the minutes
Vice-Mayor Mosley, Chair of the Boards & Commissions Committee, said that this is the consideration of appointing members to the Civil Service Board.. The terms of Carol Goins (current Chair) and Carter Webb expire on May 21, 2025. In addition, City Council must appoint a Chair. Carol Goins and Richard Deavereaux are interested in the seat of Chair. The following individual applied for the vacancy: James Wornall Jr. The Chair recommended reappointment of Carter Webb.
Copied word for word from the minutes (“…” marks words left out).
Motion to amend the agenda to add a Consent item amending the 2025-26 Council meeting calendar (cancel April 17 briefing and April 22 formal meeting)
Passed7–0 · Moved by Maggie Ullman, seconded by Kim Roney
All members present voted yes.
Key facts
At the request of Mayor Manheimer, Councilwoman Ullman moved to amend the City Council agenda to add to the Consent Agenda a motion amending the 2025-26 City Council meeting agenda to (1) delete the April 17, 2025, Agenda Briefing Workession; and (2) delete the April 22, 2025, City Council formal meeting.
Replacement of Metropolitan Sewerage District's Carrier Bridge Pump Station
he reviewed the scope of work, at an estimated cost of approximately 105M. … MSD has been working with the City of Asheville to speed up construction activities that are in and around the river to coincide with restoration efforts - formalized Memorandum of Understanding dated February 28, 2025 … The river crossings are anticipated to be completed in the first quarter of 2027.
Presented by Hunter Carson, MSD’s Engineering Director.
The follow-up meeting will be in late April or early May. … Mayor Manheimer thanked these talented, professional community members for their time and expertise in providing this report to the City.
[Elyse Marder] then gave a brief introduction of the RWG, which was formed in 2022 in response to a staff-led proposal to radically reduce the number of boards and align the remaining boards with a relevant Council Committee. … prepared a report detailing our 28 recommendations. The main theme included goal setting, board review; communicating with City Council; technology; training; representation and participation; and board management.
Presented by Elyse Marder, member of the Realignment Working Group (RWG).
Councilwoman Roney said that because we have a lot of work ahead, and many hands who want to help, when is our follow up meeting for board officers? … Councilwoman Roney thanked members of the RWG and clarified that the work previously under Council's Boards & Commissions Committee will now be under a new Council Committee of Policy, Finance, and Infrastructure that is also overseeing boards and equity moving forward in a monthly work session.
Councilwoman Ullman invited the members of the RWG to the follow-up meeting with Chairs and Co-Chairs to see how their recommendations regarding restructuring, goals and ways to collaborate together are progressing.
Open public comment 6 topics, as the minutes list them
raise awareness regarding June 1 to 7 free Clinic and Flood Recovery effort entitled "Hope Through the Storm" and request for notifying potential volunteers for the event
advocate for a design change of the I-26 connector project and concern for I-26 flyover and impacts to the East/West Neighborhood
need to reinstate the Urban Forestry Commission
urge Council to take the Realignment Working Group’s recommendations seriously
history of hatred of the Jewish community
conservation easements
What staff answered afterwards 7 questions from council, answered in the city’s follow-up memo
Councilmeeting, Apr 8, 2025 Public Safety
What other NC communities have implemented a 4th shift and reduced firefighter working hours?
Staff:The report that was completed by former Chief Burnette indicated that Waynesville NC is currently utilizing a 4th shift and Greenville NC is halfway through the process of implementing the 4th shift. Finance staff reached out directly to Budget contacts in Charlotte, Raleigh, Concord, High Point, Durham, Winston Salem, Wilmington, Rocky Mount, and Chapel Hill. All of these municipalities are currently operating on a 56 hour schedule (same as Asheville). Fayetteville reported that they use a 51 hour schedule. According to Budget staff in these cities, none of them are actively contemplating a move to a different shift schedule.
Councilmeeting, Apr 8, 2025 Public Safety
How many firefighters are new? Is there a retention issue in the department that could lead to a potential safety issue?
Staff:The average employee working under the Fire pay plan has been working for the City for almost 10 years. This includes firefighters, senior firefighters, and supervisors. They run 2 classes of about 15 people each year to fill vacant firefighter positions as people get promoted to higher ranks, retire, and/or leave the organization. AFD has been very successful in recruiting to fill vacant positions so their vacancy rate has been very low over the past few years.
Councilmeeting, Apr 8, 2025 Potential Savings
Are there other annual direct allocations to area non-profits and organizations that we don't see or review? Can we get a list of who and how much? And how long have they been getting the funding? Do they provide annual reports or any follow-up for the funding? Are the monies restricted to agreed-upon activities like we do with other partners?
Staff:The City provides financial support to a handful of local organizations through the General Fund, as detailed in the attached chart. For the most part, these organizations are required to follow a reporting process that is the same or very similar to the Strategic Partnership Grants reporting process. This requires them to provide quarterly updates to the City. Please see the attached document for further details.
Councilmeeting, Apr 8, 2025 Potential Savings
Are there other items out there lingering like retiree health insurance (OPEB) that are still captured on a cash basis?
Staff:Like many local governments in NC, the City offers a Law Enforcements Officers Special Separation Allowance. This defined benefit pension plan provides retirement benefits to the City’s qualified sworn law enforcement officers. As of December 31, 2023 the City had 31 retirees receiving benefits through this plan. The City has chosen to fund the Separation Allowance on a pay-as-you-go basis and expenditures are made from the General Fund. Fiscal year 2024 expenses totaled $595k.
Councilmeeting, Apr 8, 2025 Potential Savings
What are the fund balances for the City’s Enterprise Funds?
Staff:The table below shows the City’s fund balance policy for each Enterprise Fund as well as the Fiscal Year 2024 year-end fund balance information for each of those funds. Some specific things to note about each of these funds include: i. Water & Stormwater - Since these are utility enterprise funds, the City is not allowed to transfer funding from either to the General Fund. ii. Street Cut - Staff has recommended using $400k-$600k from the Street Cut fund balance to help balance the General Fund budget in Fiscal Year 2026. The remaining money in the Street Cut fund balance was collected from that fund’s degradation fee and is reserved for street resurfacing in the capital budget. iii. Parking - It is anticipated that the Parking fund balance of $1.8M will likely decrease substantially at the end of the current fiscal year due to the revenue loss in that fund this year. iv. Transit - Fund balance in Transit consists of a mix of local and restricted intergovernmental dollars so this funding can not be utilized for other purposes. Also it should be noted that the timing of federal reimbursements for transit operations can have a substantial impact on year end balances in that fund so it is advisable to maintain a balance above the policy target in order to provide a cushion for these types of timing issues. v. Harrah’s - Staff is currently planning to utilize the $2.8M in Harrah’s fund balance to help fund upcoming maintenance and upgrade projects that are likely to be required as part of the continuing contract with SoCon.
Councilmeeting, Apr 8, 2025 Potential Savings
Have we alerted anyone who has multi-year funding for SPG that that is being paused?
Staff:In round 2 of the Strategic Partnership Grants program, there were two grant recipients who received multi-year grants. Those contracts have all been encumbered, and they are due to close out at the end of this fiscal year. All the current grants from round 4 are one-year and will close out at the end of this fiscal year. As part of the work to overhaul SPG, staff had considered adding a multi-year option to the SPG program but did not finalize that direction. Instead, staff began to focus SPG program enhancements on reporting and understanding the impact.
Councilmeeting, Apr 8, 2025 Potential Savings
Are any additional revenue updates coming?
Staff:Finance does not have any new data that would lead us to increase revenue projections for next year, but we are continuing to receive property tax updates from the County and sales tax updates from the State. We are also monitoring the national economic situation, which has the potential to impact revenue if the current economic downturn continues. This will not only affect revenues but would impact all capital projects, the purchase of materials and supplies, fleet purchases and parts, and more. If there are changes to the revenue projections for next year, they would likely lead to a revenue decrease.
Work session, Tuesday, Apr 8, 2025 the agenda briefing after this meeting · 11 am–11:26 am
Other business
Agenda Briefing Worksession
City Council held an agenda briefing worksession to discuss the upcoming and future agenda items. All Council committees will continue to remain on pause as City Council works through post-Helene priorities and goals.
Staff briefed on
Capital Projects Budget
Budget meeting, Tuesday, Apr 8, 2025 3 pm–4:53 pm
Report
Budget Worksession
It was the consensus of Council to support this path forward on compensation (3% hybrid option with APD pay plan, and AFD 4th shift); and the salary increases and 15% fund balance property tax scenario with the loan of an estimated $1.50 cent property tax rate increase with the CDL loan included.
Staff has continued to review fiscal year (FY) 26 financial projections and has identified additional opportunities to close the General Fund budget gap … Overall FY26 General Fund revenues estimates have increased by $900k. … Overall the opioid and vacancy adjustments will reduce FY26 General Fund expenditure estimates by $498k.
Presented by Tony McDowell, Finance Director; Lindsay Spangler, Budget Manager; Debra Campbell, City Manager.
Financial Assumptions - General Fund CIP budget capacity is $20 to $25M per year … recapped the 2024 General Obligation (GO) Bond categories of $20M in housing affordability; $20M in parks and recreation; $20M in transportation; and $20M in public safety facilities. … Simple projects are straightforward repairs or replacements that follow FEMA’s one-for-one restoration requirement.
Presented by Jade Dundas, Interim Assistant City Manger.
This resource, to the best of its ability, is copied word for word from the official minutes, “…” marks words left out, and [brackets] a name the minutes give elsewhere. The minutes are the record. Staff answers are quoted from the city’s follow-up memos. Staff report details are quoted from the city’s meeting documents, prepared before the vote.