Asheville City Council recorded 24 votes at its regular meeting on April 28, 2026; none drew a no vote. Most items fell under Utilities & Infrastructure, Zoning & Land Use and Budget & Finance.
Met: 5 pm–7:07 pm. Voting: Bo Hess, Esther E. Manheimer, S. Antanette Mosley, Kim Roney, Sheneika Smith, Sage Turner, Maggie Ullman.
Votes 24 recorded · 7 substantive · none split
Item G · RES 26-71 / ORD 5211 · Utilities & Infrastructure · Resolution · consent agenda
Resolution authorizing a contract with Morgan Corporation for the North Fork Dam Helene Repairs Construction Project; budget amendment
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Key facts
$865,086North Fork Dam Tropical Storm Helene Repairs
$129,76315% contingency
$994,849totaling
Morgan Corporationcontractor or recipient
From the staff report
Adoption of a resolution authorizing the City Manager to execute a contract with Morgan Corporation for the North Fork Dam Tropical Helene Repairs; and the associated budget amendment, in the amount of $994,849.
$865,086construction contract
$129,76315% contingency
$994,849for a total of $994,849
$895,364Fed Revenue Distribution - Federal Emergency Management Agency
$99,485State Revenue Distribution - Federal Emergency Management Agency
FEMA Public Assistance (90%), state funds (10%)funding source
Competitive bid · 3 responsesThe lowest, responsive, responsible bidder was Morgan Corporation, from Duncan, South Carolina, at the amount of $865,086.00. The following bids were received: Morgan Corporation $865,086.00 Zachary Construction Corporation $1,350,000.00 Crowder Construction $2,434,705.00
Fiscal impact
The contract is $865,086 with a 15% contingency of $129,763, for a total of $994,849. The project is expected to be fully reimbursed through a combination of FEMA Public Assistance (90%) and state funds (10%).
Staff’s stated reasons
The project returns the auxiliary spillway and other associated assets to their original design and full usefulness.
The replacement of the Fusegate will help return water storage to its normal levels.
City Code sections
N.C.G.S. sec. 143-129, N.C.G.S. secs. 160A-20.1, 160A-311, and 160A-312
Staff: Leslie Carreiro, Water Resources Assistant Director.
Description in the minutes
- Resolution authorizing the City Manager to execute a contract with Morgan Corporation for the North Fork Dam Helene Repairs Construction Project
Ordinance Number 5211- Budget amendment for the North Fork Dam Helene Repairs Construction Project
- On September 27, 2024 Tropical Storm Helene and associated flooding activated the auxiliary spillway at the North Fork Water Treatment Plant.
In order to pass a larger volume of raw water into the auxiliary spillway activation (sacrifice) of Fusegate P4 was required.
The Auxiliary spillway operated as designed and reduced the reservoir to a safe level protecting the community, Burnette Reservoir and Dam.
This project will replace the P4 Fusegate in the North Fork Auxiliary spillway, and repair other Helene associated damages to both the Auxiliary and Primary spillway structures.
Motion authorizing the City Manager to execute a contract with Morgan Corporation for the North Fork Dam Tropical Storm Helene Repairs at cost of $865,086 with a 15% contingency of $129,763 totaling $994,849; and the associated budget amendment, in the amount of $994,849.
Copied word for word from the minutes (“…” marks words left out).
Item I · RES 26-73 / ORD 5212 · Utilities & Infrastructure · Resolution · consent agenda
Resolution authorizing a contract with W.K. Dickson & Co. (Ardurra) for stormwater infrastructure design; budget amendment
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Key facts
$1,001,899design and engineering services for Helene Recovery - Stormwater Repairs Professional Services - Project A
$150,28515% contingency
$1,152,184approval of a budget amendment
W.K. Dickson & Co., LLC d/b/a Ardurra Group North Carolinacontractor or recipient
FEMA PA and Hazard Mitigation Grant Program (HMGP) grantsfunding source
From the staff report
Adoption of a resolution authorizing the City Manager to enter into a contract with W.K. Dickson & Co., LLC d/b/a Ardurra Group North Carolina ("Ardurra"), in the amount of $1,001,899 for design and engineering services for Helene Recovery - Stormwater Repairs Professional Services - Project A, to repair or replace damaged stormwater infrastructure; and further authorizing the City Manager to execute any change orders that may arise during the project up to the 15% contingency amount of $150,285; and approval of a budget amendment of $1,152,184 to add federal and state funds and appropriated Stormwater fund balance to the Stormwater Capital Projects Fund.
$1,001,899in the amount of $1,001,899 for design and engineering services for Helene Recovery - Stormwater Repairs Professional Services - Project A
$150,28515% contingency
$1,152,184budget amendment
$104,027appropriates $104,027 in Stormwater fund balance to pay for work that is not FEMA eligible
Federal Emergency Management Agency - Public Assistance (FEMA-PA) program, Federal Emergency Management Agency - Hazard Mitigation Assistance (FEMA-HMA), Stormwater fund balancefunding source
Request for Qualifications · 15 responsesOn December 19, 2025, staff posted a Request for Qualifications (298-FY26-PW-RFQ-Stormwater Repairs - Helene Recovery Project) for the services to design stormwater repairs. The qualifications were due January 29, 2026. Fifteen submissions were received and evaluated for each of the three projects by a four-member selection committee from the Public Works and Parks and Recreation departments. … 9 MWBE vendors were notified of the City of Asheville professional services opportunity. Ardurra was selected by staff as the best-qualified firm
Fiscal impact
This project is expected to be reimbursed by the Federal Emergency Management Agency - Public Assistance (FEMA-PA) program and by Federal Emergency Management Agency - Hazard Mitigation Assistance (FEMA-HMA). … The attached budget amendment also appropriates $104,027 in Stormwater fund balance to pay for work that is not FEMA eligible.
Staff’s stated reasons
Repair of damaged stormwater infrastructure
Upgrading of existing pipes to meet current City Codes in size and material
Construction impacts resulting in detour routes for residents, visitors, and property owners.
City Code sections
N.C.G.S. § 143-64.31
Staff: Amy Deyton, Director, Public Works Department; Derek Wainscott, Stormwater Division Manager, Public Works.
Description in the minutes
- Resolution authorizing the City Manager to enter into a contract with W.K. Dickson & Co., LLC d/b/a Ardurra Group North Carolina ("Ardurra"), for design and engineering services for one of three City-wide recovery projects to repair or replace damaged stormwater infrastructure; and further authorizing the City Manager to execute any change orders that may arise during the project up to the 15% contingency amount
Ordinance Number 5212- Budget amendment, in the amount of $1,152,184, to add federal and state funds to the Stormwater Capital Projects Fund for the W.K. Dickson & Co., LLC Contract
- The City of Asheville has a need to hire qualified engineering professionals to help the City rebuild its infrastructure after severe damage from Tropical Storm Helene.
There are roughly fifty (50) locations in the City-wide Stormwater Repairs Helene Recovery Project where standalone stormwater infrastructure was damaged from the storm, including pipes, catch basins, junction boxes, head/end walls, inlets, and outlets.
In an effort to accelerate the project schedule, the standalone locations were separated into three design projects (Project A, B, and C).
The sites were primarily grouped geographically and by work type (e.g. stormwater control measures).
On December 19, 2025, staff posted a Request for Qualifications (298-FY26-PW-RFQ-Stormwater Repairs
Helene Recovery Project) for the services to design stormwater repairs.
The qualifications were due January 29, 2026. Fifteen submissions were received and evaluated for each of the three projects by a four-member selection committee from the Public Works and Parks and Recreation departments.
Project A is one of three contracts (Project A) to repair stormwater infrastructure damages from Tropical Storm Helene. Project A includes locations primarily in the north and west areas of Asheville and includes 25 pipes.
The scope of design and engineering services encompasses:
Analysis of the stormwater system, including, but not limited to, pipe sizing and potential end treatments for mitigation.
Repair or replacement of any related embankment, subgrade, roadway pavement, curb and gutter, concrete sidewalk, handrails, and armoring or energy dissipation which is disturbed by the pipe replacement or repair.
Recommendations on mitigation work and opportunities for resiliency.
Preparation of all necessary regulatory and environmental compliance documentation.
Final construction documents ready for bid advertising.
Funding for this project is anticipated to come from multiple sources, including FEMA PA and Hazard Mitigation Grant Program (HMGP) grants.
City funds may be required to cover the costs for one of the contract sites, as it does not qualify for Federal Emergency Management Agency
Public Assistance (FEMA-PA) funding.
The Federal Emergency Management Agency (FEMA) proposed Schedule: Design and Permitting: May 2026
February 2027 Construction Bid: March 2027
Motion to adopt a resolution authorizing the City Manager to enter into a contract with W.K. Dickson & Co., LLC d/b/a Ardurra Group North Carolina ("Ardurra"), in the amount of $1,001,899 for design and engineering services for Helene Recovery
Stormwater Repairs Professional Services
Project A, to repair or replace damaged stormwater infrastructure; and further authorizing the City Manager to execute any change orders that may arise during the project up to the 15% contingency amount of $150,285; and approval of a budget amendment of $1,152,184 to add federal and state funds and appropriated Stormwater fund balance to the Stormwater Capital Projects Fund.
Copied word for word from the minutes (“…” marks words left out).
Item IV-A · ORD 5218 · Zoning & Land Use · Public hearing
Ordinance to conditionally rezone 50 Coxe Ave from Central Business District to Central Business Expansion - Conditional Zone (with amendment to condition 12)
Passed7–0 · Moved by S. Antanette Mosley, seconded by Kim Roney
All members present voted yes.
11 spoke · changed before the vote · 3 council remarks
Recommendations
Council’s vote matched the city staff recommendation.
City staff: Approve — Staff recommends approval of this rezoning request based on the reasons stated above.
Technical Review Committee: Approve with conditions
Design Review Committee: Approve with conditions
Planning & Zoning Commission: Approve with conditions
Public hearing 6:37 pm–6:53 pm · advertised Apr 17, 2026 and Apr 24, 2026
11 spoke in favor · 0 spoke against
ForNate Pennington · for the applicant, Buncombe County — After that discussion, Buncombe County Planning Director Nate Pennington agreed to the following condition 12 amendment:
ForPaul Kunze · for the applicant, Design team — Mr. Paul Kunze, member of the design team, explained the results of their Traffic Impact Analysis, which they would be happy to share with the City.
One individual spoke in support of the project; however, urged City Council to add a condition that the developer ask the Asheville Police Department to provide recommendations on how they can build the large pedestrian overhang area to accommodate safety due to the close proximity to the Transit Center. The minutes name 2 of the 11 speakers.
What council members said 3 remarks from 3 members
QuestionWhen Councilwoman Roney asked if there is a plan for renewable energy or anything about the project that would prohibit it in the future, the attorney for Harmony Housing Affordable Development said that their plan includes solar and green space.
QuestionIn response to Councilwoman Ullman, Mr. Paul Kunze, member of the design team, explained the results of their Traffic Impact Analysis, which they would be happy to share with the City.
ConcernIn response to Councilman Hess, Mr. Kunze said that they are still in the design phase to make sure the areas at the entrance and exit are well lit and safe as possible, but will have to leave it up to Buncombe County on the leasing agency that takes over.
The minutes record no remarks on this item from Esther E. Manheimer, S. Antanette Mosley, Sheneika Smith and Sage Turner.
Changed before the vote 1 change recorded
Offered by the applicantAll Units shall be designated as ‘affordable’ at not less than 80% of AMI for a period of 30 years. The applicant shall further use its best efforts to meet this condition as more specifically delineated as follows: 11 Units at 20% AMI; 35 Units at 30% AMI; 113 Units at 60% AMI; and 44 Units at 80% AMI.
CBD → Central Business Expansion - Conditional Zonezoning, from → to
209 units203 of them affordable
All 203 units (100%) will be designated affordable for a minimum of 30 years; and All 203 units (100%) will be designated affordable to those earning 80% or less of Area Median Income (AMI)affordability
Harmony Housing Affordable Developmentapplicant
for a period of 30 yearsterm
Presented by Will Palmquist, Principal Planner.
From the staff report
Adoption of an ordinance to conditionally rezone the properties located at 50 Coxe Ave from Central Business District (CBD) to Central Business Expansion - Conditional Zone (CBD EXP-CZ).
Petitioner(s): Paul Kunzeasked for this item
Central Business District (CBD) → Central Business Expansion - Conditional Zone (CBD EXP-CZ)zoning, current → requested
1.6 acres50 Coxe Ave
Downtownfuture land use designation
Buncombe Countyowner
Paul Kunzeapplicant
9648-39-4540parcel ID (PIN)
Fiscal impact
N/A
Staff’s stated reasons · approve
The proposed development supports a number of goals in the Living Asheville Comprehensive Plan, including: Encourage Responsible Growth - by providing infill development in targeted growth areas (p. 131). Increase Mixed-Use Development Along Transit Corridors - by incentivizing redevelopment, especially mixed-use development that contains housing, within identified transit-supportive centers (p. 135). Increase and Diversify the Housing Supply - by increasing the supply of housing, including affordable housing (pp. 179 & 183) in proximity to schools, transit and parks (pp. 246 & 251).
The proposed development is compatible with the Future Land Use designation of "Downtown"
The proposed multi-family project is compatible with the surrounding land uses, including: Existing multi-family residential, commercial, and institutional uses in the nearby vicinity. Proposed microhousing project directly to the east of the project site known as Aston & Sawyer Microhousing.
Before it reached Council
Technical Review Committee, March 2, 2026: approve with conditions
Design Review Committee, March 19, 2026: approve with conditions — approved with the following conditions: 1) Recommend reduction to the size of Coxe Ave garage door, and Sawyer St garage dumpster door, 2) Recommend considering planting selection in the covered pavilion area in regards to the species' ability to thrive in all seasons, 3) Recommend redesigning the retail glass on the Coxe Ave elevation and the brick on the south elevation, 4) Consider that the full portion of the proposed green roof be used to manage stormwater, 5) Consider ways to mitigate noise impacts from nearby entertainment uses, including the possibility of a noise easement, 6) Considering utilizing the area to the south of building for increasing vegetation and active outdoor space, with appropriate lighting, and 7) Consider vegetation on the roof of the 1st story portion of the building along Coxe Avenue.
Planning & Zoning Commission, April 1, 2026: approve with conditions (7–0) — approved with the following conditions: 1) Recommendation to investigate with the City Traffic Engineer the potential impacts on multimodal safety on Ravenscroft Dr and the intersection of Ravenscroft Dr and Hilliard Ave, i.e. investigating the conversion of Ravenscroft Dr into a one-way street, and removing the wall at the northwest corner of the intersection of Ravenscroft Dr and Hilliard Ave; 2) Recommendation for the City to investigate designating the on-street parking on Ravenscroft Dr as resident only; 3) Recommendation that the City Traffic Engineer study the intersection of Ravenscroft Dr and Sawyer St, specifically for pedestrian safety; and, 4) That the applicant investigate the opportunity to add more trees to the site, including at the south side of the building.
Current and requested zoning compared
Provision
Central Business District (CBD)
Central Business Expansion - Conditional Zone (CBD EXP-CZ)
Building height
Maximum building height for the Tallest Height Zone in the CBD district 265'. The minimum building height in the CBD district is two stories.
The proposed building height is approximately 68' as measured in the CBD district, with an overall height of approximately 84' measured to the top of the roof. A portion of the building fronting along Coxe Ave is proposed to be one story in height.
Density
No maximum residential density
The proposed project's density is approximately 127 units/acre.
Tree Canopy Preservation
The project site is classified as "Urban" under the Tree Canopy Preservation standards, with a classification of "Class A", resulting in a 10% canopy requirement.
The project is requesting a technical modification for tree canopy preservation requirements, reducing the 10% requirement to 1.2%.
Vehicle parking
452 space maximum
A total of 121 parking spaces are proposed within a two-level parking structure.
Conditions
1. The property included in the rezoning is shown on the site plan and is identified on the Buncombe County tax map as PINs 9648-39-4540, 9648-39-4353, and 9648-39-6366 and is 1.6 acres.
2. Pursuant to this ordinance, the entire subject property is rezoned to Central Business Expansion - Conditional Zone (CBD EXP - CZ), and approval is limited to the proposed project ("Project") described herein.
3. The Project will include a new multi-family building with a maximum of 203 residential units.
4. The new building will be a maximum of seven stories. Building heights will not exceed 75 feet, as measured from the primary pedestrian entrance to the surface level of the highest occupied floor.
5. Vehicular access to the Project will be provided by two driveways on Coxe Ave and Ravenscroft Dr.
6. The Project will include a maximum of 125 parking spaces.
7. New sidewalks along Coxe Ave, Sawyer St, Aston St, and Ravenscroft Dr will be a minimum width of 10'.
8. Any recommendations required by the approved Traffic Impact Analysis will be implemented prior to the Project receiving a Certificate of Occupancy.
9. Two crosswalks and associated curb ramps, designed and built to City standards, will be installed at the intersection of Sawyer St and Ravenscroft Dr, specifically along the western and southern sidewalks of the intersection.
10. Landscaping will be provided on the site according to standards required by Section 7-11-3 of the UDO and as shown on site plans.
11. Tree canopy preservation requirements will be satisfied as required by UDO Article XIX.
12. Affordable housing is included in the Project: 1. All 203 units (100%) will be designated affordable for a minimum of 30 years. 2. All 203 units (100%) will be designated affordable to those earning 80% or less of Area Median Income (AMI). 3. The rent and income limits will follow the Affordable Housing Standards determined annually by the Department of Housing & Urban Development (HUD). 4. An Affordable Housing Deed Restriction setting forth the Affordable Housing Requirements will be provided by the City and will be filed and recorded by the property owner in the Buncombe County Register of Deeds prior to the project receiving final zoning permit
13. Except as modified herein, the Project shall comply with all conditions outlined in the March 2, 2026 TRC Staff Report.
14. The Project includes technical modifications: 1) Minimum building height of one-story for the portion of the proposed building fronting on Coxe Avenue. 2) Reduction in the Tree Canopy Preservation requirement from 10% to 1.2%.
15. The Project will undergo final review by the TRC prior to issuance of any permits.
16. All proposed site and exterior building lighting must meet the outdoor lighting requirements found in UDO Sec. 7-11-10.
17. The building design, site design and orientation on site must substantially comply with the approved site plan and elevations which are incorporated herein by reference.
18. All applicable required local, state, and federal permits and approvals must be obtained prior to initiation of construction.
19. The conditional zoning will be valid for five years from the date of approval by City Council with action taken to obtain building permits within this 60-month period.
City Code sections
UDO Sec. 7-11-3, UDO Article XIX, UDO Sec. 7-11-10
Exhibit D - Site Plans & Elevations.pdf ↗: 50 COXE AVE. AFFORDABLE HOUSING 50 COXE AVENUE ASHEVILLE, NORTH CAROLINA 28801 … DESIGN REVIEW COMMITTEE / SCHEMATIC DESIGN PACKAGE
Ordinance - 50 Coxe Ave.pdf ↗: recorded in Deed Book 5347, Page 1616, and Deed Book 5606, Page 1279Said rezoning is subject to the conditions set out in Exhibit "E" (project conditions agreed to by City and applicant that must be met for conditional zoning), and the site plan(s) and elevations as shown in Exhibit "D" (site plan(s), landscape plan, elevations)
TRC Staff Report - 50 Coxe Ave Affordable Housing (26-00515PZ).pdf ↗: Current Recommendation: Administrative Revisions RequiredA Traffic Impact Analysis (TIA) is required based on estimated 100+ peak hour trips and has been submitted. Review comments will be separate from TRC. Improvements required from the TIA must be complete or under construction prior to issuance of any Certificate of Occupancy (UDO 7-11-6-c).The project proposes a new, 7-story, mixed-use development with 203 multi-family units and approximately 9,000 SF of retail space.
DRC Staff Report - 50 Coxe Ave Affordable Housing.pdf ↗: Staff supports the proposed building design of the 50 Coxe Ave Affordable Housing project and recommends approval as the project is in alignment with requirements and guidelines.The building frontage along Coxe Ave is proposed along more than 80% of the frontage, notwithstanding the recess at the first-story which reduces the frontage of the lot to approximately 80%. … Vehicular access to the parking decks are proposed off of Coxe Ave, a Key Pedestrian Street, as well as Ravenscroft Dr. … The design proposes a portion of the building that is one-story in height along Coxe Ave as it relates to the required building stepback.Materials: As indicated on the project submission, the main building materials will be: 1) brick veneer in running bond pattern; 2) fiber cement siding; 3) cementitious boards with metal reveal, and; 4) glass storefront system.
PZC Staff Report - 50 Coxe Ave Affordable Housing.pdf ↗: Bicycle Parking Spaces: 10% of number of dwelling units = 11 81 spaces Open Space: n/a n/a Impervious Surface Area: None 96.2% Sidewalks: 10'-wide back of curb 10'- to 12'-wideStreet trees are required as being one small maturing tree for every 30 linear feet of property abutting abutting Aston St, Sawyer St, and Ravenscroft Dr where overhead utilities are present, resulting in 15 trees, as well as one large maturing tree for every 40 linear feet of property abutting Coxe Ave, where no overhead utilities are present, resulting in 8 trees.Median Household Income $27,768 $66,032 … CJI Score: 21 out of 25 21
PZC Recommendation - 50 Coxe Ave Affordable Housing.pdf ↗: The Planning and Zoning Commission recommended approval and voted 7-0.Vote: 7-0 Motion: Vice-chair Seickel Second: Commissioner Faircloth In Favor: Chair Barton, Vice-chair Seickel, Commissioners Anzollitto, Bell, Broughel, Faircloth, and Zuevskaya Opposed: None
Staff: Stephanie Monson Dahl, Planning and Urban Design Director; Chris Collins, Assistant Director; Will Palmquist, AICP, Principal Planner.
Description in the minutes
- Ordinance to conditionally rezone property located at 50 Coxe Ave from Central Business District to Central Business Expansion
Conditional Zone
Principal Planner Will Palmquist said that this is the consideration of a conditional zoning request for the property located at 50 Coxe Ave from Central Business District to Central Business Expansion
Conditional Zone for the purposes of constructing a 209-unit mixed-use development. This public hearing was advertised on April 17 and 24, 2026. Project Location and
Contacts:
The project site totals 1.6 acres located at 50 Coxe Ave (PINs 9648-39-4540, 9648-39-4353, 9648-39-6366).
Owner: Buncombe County Summary of Petition: Project Site
The project area consists of three properties totalling 1.6 acres located at 50 Coxe Ave and is identified in the Buncombe County land records as PINs 9648-39-4540, 9648-39-4353, 9648-39-6366.
The site is currently zoned Central Business District (CBD).
The current use of the site is the administrative offices of Buncombe County and associated surface parking.
Given the size of the proposed project, a conditional zoning to the Central Business Expansion
Conditional Zone (CBD EXP
CZ) district is required.
Based on the Living Asheville Comprehensive Plan Future Land Use Map (FLUM) the property is currently designated “Downtown”. A change to the Future Land Use Map (FLUM) will not be required. Overall Project Proposal
New building construction includes a new, 7-story, mixed-use development with 203 multi-family, affordable units and approximately 5,000 SF of retail space.
The project’s total building area is 251,059 square feet.
A total of 121 parking spaces are proposed within a two-level parking structure. Technical Modifications
The project is seeking technical modifications to development standards through the conditional zoning process including:
Minimum building height of one-story for the portion of the proposed building fronting on Coxe Avenue.
Reduction in the Tree Canopy Preservation requirement from 10% to 1.2%. Site Layout and Design
Maximum building height for the Tallest Height Zone in the CBD district 265’. The minimum building height in the CBD district is two stories. The proposed building height is approximately 68’ as measured in the CBD district, with an overall height of approximately 84’ measured to the top of the roof. A portion of the building fronting along Coxe Ave is proposed to be one story in height.
The project is seeking a technical modification for building height minimums.
There is no maximum residential density in the CBD district.The proposed project’s density is approximately 127 units/acre. Access, Sidewalks and Parking
The project site has frontages on multiple streets including Coxe Ave, Aston St, Sawyer St, and Ravenscroft Dr. There is also a public alley between Sawyer and Aston Streets which is proposed to be improved and would facilitate one-way traffic to the north.
The main vehicle access to the site will be via access to parking decks off Coxe Ave and Ravenscroft Dr.
The project site is across the street from the ART Bus Transit Station.
The project proposes new sidewalks along its frontages varying in width between 10’-12’, and along the public alley with a width of 6’.
The project proposes two new crosswalks and associated curb ramps at the intersection of Sawyer St and Ravenscroft Dr, specifically along the western and southern sidewalks of the intersection.
The project is coordinating closely with the Coxe Avenue Streetscape project which proposes a new streetscape design for the entirety of Coxe Avenue from Patton to Southside Aves. The project will incorporate and construct this section of the streetscape, as designed by the streetscape project, with appropriate modifications, as needed, for the project elements such as curb cuts and building entrances.
The public right-of-way on Sawyer St underneath the proposed building was officially closed via City Council Resolution 24-215, adopted September 24, 2024. The purpose of the ROW closure was to close the street to public, vehicular use, in order to build the portions of the building above. This area will not be open to vehicular traffic, and will instead maintain public pedestrian access between Coxe Ave and the remainder of the open Sawyer St at the dog-leg intersection with the public alley.
The proposed parking deck contains a total of 121 spaces on two separate levels without access between them. The lower level of the deck is accessed from Coxe Ave and spans the first story of the lower portion of the proposed building with a total of 50 spaces. The upper level of the deck is accessed from Ravenscroft Dr and spans the second story of the upper and lower portions of the proposed building with a total of 71 spaces. Landscaping / Open Space / Tree Canopy
Minimal landscape requirements apply for projects in the CBD district, including street trees.
The project proposes to meet partial Tree Canopy Preservation requirements through new tree plantings on the site. The project site is classified as "Urban" under the Tree Canopy Preservation standards, with a classification of “Class A”, resulting in a 10% canopy requirement.
The project is requesting a technical modification for tree canopy preservation requirements, reducing the 10% requirement to 1.2%.
The project proposes two separate green roof/amenity spaces on the 3rd floor of the building. The area on the east of the building is proposed to be a programmed amenity space with play, lounge, and grilling areas, along with plantings. The area on the south side of the building is proposed to be a green roof with incorporated stormwater retention.
These proposed amenity and green roof areas are above what is required for landscaping, open space, or stormwater management. Consistency with the Comprehensive Plan and Other Plans: Living Asheville Comprehensive Plan (2018)
The proposed development supports a number of goals in the Living Asheville Comprehensive Plan, including:
Encourage Responsible Growth
by providing infill development in targeted growth areas.
Increase Mixed-Use Development Along Transit Corridors
by incentivizing redevelopment, especially mixed-use development that contains housing, within identified transit-supportive centers.
Increase and Diversify the Housing Supply
by increasing the supply of housing, including affordable housing in proximity to schools, transit and parks.
The proposed development is compatible with the Future Land Use designation of “Downtown”, which is proposed in part, that: “Downtown continues to expand with new development and revitalization opportunities along the edges of the downtown core and via infill development,” and that, “Downtown is also an important residential area and it benefits from having year-round full-time residents. Opportunities for growing this sector of the downtown population through new development is important for the future including market-rate and affordable residential housing”.
Compatibility Analysis:
The proposed multi-family project is compatible with the surrounding land uses, including:
Existing multi-family residential, commercial, and institutional uses in the nearby vicinity.
Proposed microhousing project directly to the east of the project site known as Aston & Sawyer Microhousing.
Staff Recommendation:
Staff recommends approval of this rezoning request based on the reasons stated above. Mr. Palmquist reviewed the existing and proposed zoning, the aerial imagery, the future land use map, and the site plan, along with elevation drawings. Regarding the project conditions and technical modifications, (1) Affordable housing is included in the Project: All 203 units (100%) will be designated affordable for a minimum of 30 years; and All 203 units (100%) will be designated affordable to those earning 80% or less of Area Median Income (AMI); and (2) The Project includes technical modifications: (1) Minimum building height of one-story for the portion of the proposed building fronting on Coxe Avenue; and (2) Reduction in the Tree Canopy Preservation requirement from 10% to 1.2%. He said the (1) Technical Review Committee approved the project with conditions; and Design Review Committee approved the project with conditions; and the the Planning & Zoning Commission voted to approve the project with the condition. He then explained how the project was consistent with the Living Asheville Comprehensive Plan. He said that staff concurs with the Planning & Zoning Commission and recommends approval of the proposed conditional zoning. When Councilwoman Roney asked if there is a plan for renewable energy or anything about the project that would prohibit it in the future, the attorney for Harmony Housing Affordable Development said that their plan includes solar and green space. There was considerable discussion regarding the developer’s intent to accept Housing Authority vouchers. After that discussion, Buncombe County Planning Director Nate Pennington agreed to the following condition 12 amendment: “ All Units shall be designated as ‘affordable’ at not less than 80% of AMI for a period of 30 years. The applicant shall further use its best efforts to meet this condition as more specifically delineated as follows: 11 Units at 20% AMI; 35 Units at 30% AMI; 113 Units at 60% AMI; and 44 Units at 80% AMI.” In response to Councilwoman Ullman, Mr. Paul Kunze, member of the design team, explained the results of their Traffic Impact Analysis, which they would be happy to share with the City. In response to Councilman Hess, Mr. Kunze said that they are still in the design phase to make sure the areas at the entrance and exit are well lit and safe as possible, but will have to leave it up to Buncombe County on the leasing agency that takes over. Mayor Manheimer opened the public hearing at 6:37 p.m. One individual spoke in support of the project; however, urged City Council to add a condition that the developer ask the Asheville Police Department to provide recommendations on how they can build the large pedestrian overhang area to accommodate safety due to the close proximity to the Transit Center. Other concerns were the parking deck exit onto Ravenscroft; lighting in the neighborhood; request to convert Ravenscroft Drive into a one way; designate on-street parking for homeowners and buildings on Ravenscroft; inspect the pedestrian crossing; and the need for better pedestrian markings. Seven individuals spoke in support of this very needed project. Mayor Manheimer closed the public hearing at 6:53 p.m.
Copied word for word from the minutes (“…” marks words left out).
Item J · RES 26-74 / ORD 5213 · Utilities & Infrastructure · Resolution · consent agenda
Resolution authorizing a contract with Bolton & Menk, Inc. for stormwater infrastructure design; budget amendment
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Key facts
$1,051,020design and engineering services for Helene Recovery - Stormwater Repairs Professional Services - Project B
$157,65315% contingency
$1,208,673approval of a budget amendment
Bolton & Menk, Inc.contractor or recipient
FEMA PA and Hazard Mitigation Grant Program (HMGP) grantsfunding source
From the staff report
Adoption of a resolution authorizing the City Manager to enter into a contract with Bolton & Menk, Inc. ("Bolton & Menk"), in the amount of $1,051,020 for design and engineering services for Helene Recovery - Stormwater Repairs Professional Services - Project B, to repair or replace damaged stormwater infrastructure; and further authorizing the City Manager to execute any change orders that may arise during the project up to the 15% contingency amount of $157,653; and approval of a budget amendment of $1,208,673 to add federal and state funds and appropriated Stormwater fund balance to the Stormwater Capital Projects Fund.
$1,051,020in the amount of $1,051,020 for design and engineering services for Helene Recovery - Stormwater Repairs Professional Services - Project B
$157,65315% contingency
$1,208,673budget amendment
$107,270appropriates $107,270 in Stormwater fund balance to pay for work that is not FEMA eligible
Federal Emergency Management Agency - Public Assistance (FEMA-PA) program, Federal Emergency Management Agency - Hazard Mitigation Assistance (FEMA-HMA), Stormwater fund balancefunding source
Request for Qualifications · 15 responsesOn December 19, 2025, staff posted a Request for Qualifications (298-FY26-PW-RFQ-Stormwater Repairs - Helene Recovery Project) for the services to design stormwater repairs. The qualifications were due January 29, 2026. Fifteen submissions were received and evaluated for each of the three projects by a four-member selection committee from the Public Works and Parks and Recreation departments. … 9 MWBE vendors were notified of the City of Asheville professional services opportunity. Bolton & Menk was selected by staff as the best-qualified firm
Fiscal impact
This project is expected to be reimbursed by the Federal Emergency Management Agency - Public Assistance (FEMA-PA) program and by Federal Emergency Management Agency - Hazard Mitigation Assistance (FEMA-HMA). … The attached budget amendment also appropriates $107,270 in Stormwater fund balance to pay for work that is not FEMA eligible.
Staff’s stated reasons
Repair of damaged stormwater infrastructure
Upgrading of existing pipes to meet current City Codes in size and material
Construction impacts resulting in detour routes for residents, visitors, and property owners.
City Code sections
N.C.G.S. § 143-64
Staff: Amy Deyton, Director, Public Works Department; Derek Wainscott, Stormwater Division Manager, Public Works.
Description in the minutes
- Resolution authorizing the City Manager to enter into a contract with Bolton & Menk, Inc., for design and engineering services for one of three City-wide recovery projects to repair or replace damaged stormwater infrastructure; and further authorizing the City Manager to execute any change orders that may arise during the project up to the 15% contingency amount
Ordinance Number 5213- Budget amendment in the amount of $1,208,673 to add federal and state funds to the Stormwater Capital Projects Fund for the Bolton & Menk Inc. Contract
- The City of Asheville has a need to hire qualified engineering professionals to help the City rebuild its infrastructure after severe damage from Tropical Storm Helene.
There are roughly fifty (50) locations in the City-wide Stormwater Repairs Helene Recovery Project where standalone stormwater infrastructure was damaged from the storm, including pipes, catch basins, junction boxes, head/end walls, inlets, and outlets.
In an effort to accelerate the project schedule, the standalone locations were separated into three design projects (Project A, B, and C).
The sites were primarily grouped geographically and by work type (e.g. stormwater control measures).
On December 19, 2025, staff posted a Request for Qualifications (298-FY26-PW-RFQ-Stormwater Repairs
Helene Recovery Project) for the services to design stormwater repairs.
The qualifications were due January 29, 2026. Fifteen submissions were received and evaluated for each of the three projects by a four-member selection committee from the Public Works and Parks and Recreation departments.
Project B is one of three contracts to repair stormwater infrastructure damages from Tropical Storm Helene. Project B includes locations primarily in the east area of Asheville and includes 26 individual stormwater sites.
The scope of design and engineering services encompasses:
Analysis of the stormwater system, including, but not limited to, pipe sizing and potential end treatments for mitigation.
Repair or replacement of any related embankment, subgrade, roadway pavement, curb and gutter, concrete sidewalk, handrails, and armoring or energy dissipation which is disturbed by the pipe replacement or repair.
Recommendations on mitigation work and opportunities for resiliency.
Preparation of all necessary regulatory and environmental compliance documentation.
Final construction documents ready for bid advertising.
Funding for this project is anticipated to come from multiple sources, including FEMA PA and Hazard Mitigation Grant Program (HMGP) grants.
City funds may be required to cover the costs for one of the contract sites, as it does not qualify for Federal Emergency Management Agency
Public Assistance (FEMA-PA) funding.
The Federal Emergency Management Agency (FEMA) proposed Schedule: Design and Permitting: May 2026
February 2027 Construction Bid: March 2027
Motion to adopt a resolution authorizing the City Manager to enter into a contract with Bolton & Menk, Inc. ("Bolton & Menk"), in the amount of $1,051,020 for design and engineering services for Helene Recovery
Stormwater Repairs Professional Services
Project B, to repair or replace damaged stormwater infrastructure; and further authorizing the City Manager to execute any change orders that may arise during the project up to the 15% contingency amount of $157,653; and approval of a budget amendment of $1,208,673 to add federal and state funds and appropriated Stormwater fund balance to the Stormwater Capital Projects Fund.
Copied word for word from the minutes (“…” marks words left out).
Item M · ORD 5215 · Budget & Finance · Ordinance · consent agenda
Budget amendment of $7.2M for Helene Disaster Recovery expenses and insurance proceeds allocation
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Recommendations
Council’s vote matched the city staff recommendation.
City staff (staff report): Approve — Staff is recommending that Council amend the Helene budget by $5.1M
Key facts
$7.2 millionBudget amendment
$5.1 millionadditional Helene Disaster Recovery and Response Expenses
$2.1 millionallocation of insurance proceeds received to date related to recovery projects
$28.8 millionHelene-related budget amendments
Federal and State Emergency Management Agency reimbursementsfunding source
From the staff report
Adoption of a budget amendment in the amount of $7.2M, $5.1M for additional Helene Disaster Recovery and Response Expenses, funded with Federal and State Emergency Management Agency (FEMA) reimbursements, and $2.1M for allocation of insurance proceeds received to date related to recovery projects
$7.2 millionAdoption of a budget amendment in the amount of $7.2M
$5.1 million$5.1M for additional Helene Disaster Recovery and Response Expenses
$2.1 million$2.1M for allocation of insurance proceeds received to date related to recovery projects
$28.8 millionCity Council has approved Helene-related budget amendments totaling $28.8M
funded with Federal and State Emergency Management Agency (FEMA) reimbursements, $2,100,000 received in the Property and Liability Fund for damaged facility claimsfunding source
Fiscal impact
Staff anticipates that this $5.1M budget authorization will be fully reimbursed through federal and state disaster recovery reimbursements, and the $2.1M has already been received from our insurance carrier.
Staff’s stated reasons · approve
Spending authority from these prior Helene-related budget amendments is nearing full utilization, so additional budget is needed in order to meet State Statute requirements related to pre-audits and budget authorizations
Allows the City to budget for expenses related to Tropical Storm Helene response and recovery and be in compliance with NC General Statutes related to pre-audits
Staff: Tony McDowell, Finance Director; Becki Ogles, Assistant Finance Director.
Description in the minutes
- Budget amendment in the amount of $7.2M, $5.1M for additional Helene Disaster Recovery and Response Expenses, funded with Federal and State Emergency Management Agency reimbursements and $2.1M for allocation of insurance proceeds received to date related to recovery projects
- The City has and will continue to incur expenses related to Tropical Storm Helene Disaster Recovery and Response.
To date, City Council has approved Helene-related budget amendments totaling $28.8M.
This budget has been utilized to fund expenses related to Helene that include costs from the initial response, ongoing staff expenses, and the contract with Hagerty Consulting.
Spending authority from these prior Helene-related budget amendments is nearing full utilization, so additional budget is needed in order to meet State Statute requirements related to pre-audits and budget authorizations
Staff is recommending that Council amend the Helene budget by $5.1M to fund upcoming expenses such as a temporary Bridge for Gashes Greek and a recent obligation for vehicle and equipment repairs and replacements.
Staff is also requesting a budget amendment to appropriate $2.1M in insurance recovery funds that have already been received in our insurance internal service fund so that we can transfer that cash to the Capital Projects Fund where expenses are being recorded for Helene projects.
Motion to adopt a budget amendment in the amount of $7.2M, $5.1M for additional Helene Disaster Recovery and Response Expenses, funded with Federal and State Emergency Management Agency (FEMA) reimbursements, and $2.1M for allocation of insurance proceeds received to date related to recovery projects.
Copied word for word from the minutes (“…” marks words left out).
Item N · ORD 5216 · Economic Development · Ordinance · consent agenda
Budget amendment of $2,492,801 from the SmBiz Infrastructure grant for the Biltmore Village Historic District
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Key facts
$2,492,801SmBiz Infrastructure grant program
NC Department of Commerce SmBIZ Infrastructure Grant programfunding source
Grant funding must be spent within 36 months of the awardterm
From the staff report
Adoption of a budget amendment in the amount of $2,492,801 from the State of North Carolina's Department of Commerce's Small Business (SmBIZ) Infrastructure grant program for design and restoration of public infrastructure in the Biltmore Village Historic District.
$2,492,801On October 31, 2025, the state awarded the City of Asheville $2,492,801
NC Department of Commerce SmBIZ Infrastructure Grant programfunding source
Fiscal impact
An increase of $2,492,801 in the City's General Capital Projects Fund.
Staff’s stated reasons
Restoration of damaged city infrastructure will improve connectivity and ADA accessibility while honoring the district's historic character.
District improvements will support economic recovery of the many and varied commercial businesses within the district, as well as Biltmore Estate.
Grant funding must be spent within 36 months of the award, and will only cover restoration work on a handful of streets in the district; additional funding will be needed to expand restoration work to other streets within the district and might not be accomplished in this project.
Staff: Stephanie Dahl, Planning and Urban Design Director; Alex Cole, Urban Planner III.
Description in the minutes
- Budget amendment in the amount of $2,492,801 from the State of North Carolina’s Department of Commerce’s SmBiz Infrastructure grant program for design and restoration of public infrastructure in the Biltmore Village Historic District.
- On August 26, 2025, City Council adopted a resolution authorizing the City Manager to apply for funding from the NC Department of Commerce SmBIZ Infrastructure Grant program to restore and repair infrastructure in Biltmore Village; and further authorized the City Manager to accept said grant funds if awarded and to enter into any agreement necessary for grant acceptance.
On October 31, 2025, the state awarded the City of Asheville $2,492,801 to work with a qualified team of professionals on design, development and restoration/construction of infrastructure in Biltmore Village, including repair/replacement of brick sidewalks, ADA ramps, granite curbing and street trees and landscaping.
Restoration of damaged city infrastructure will improve connectivity and ADA accessibility while honoring the district’s historic character.
District improvements will support economic recovery of the many and varied commercial businesses within the district, as well as Biltmore Estate.
This project will fulfill multiple adopted City plan goals and is aligned with Helene recovery goals.
Grant funding must be spent within 36 months of the award, and will only cover restoration work on a handful of streets in the district; additional funding will be needed to expand restoration work to other streets within the district and might not be accomplished in this project.
A key point of early collaboration with the community is a facilitated process to consider the needs for ADA accessibility and tree replacement within any final design.
It is anticipated that the initial design phase will begin in Summer 2026.
Project implementation will also need to be closely coordinated with the Transportation Department's street light restoration project.
Motion to adopt a budget amendment in the amount of $2,492,801 for funding from the NC Department of Commerce Small Business (SmBIZ) Infrastructure Grant program to restore and repair infrastructure in Biltmore Village.
Copied word for word from the minutes (“…” marks words left out).
Ordinance amending Article VI, Regulation of Graffiti, of Chapter 10, Nuisances, to amend the definition of graffiti (second and final reading)
Passed7–0 · Moved by Maggie Ullman, seconded by Bo Hess
All members present voted yes.
Key facts
Mayor Manheimer said that public comment on this item was accepted on April 14, 2026, and it is being voted on its second and final reading since it includes a criminal penalty.
From the staff report
Adoption of an ordinance amending Article VI, Regulation of Graffiti, of Chapter 10, Nuisances, of the Code of Ordinances to Amend the Definition of "Graffiti"
City leadership has expressed interest in easing restrictions on street and sidewalk chalk.asked for this item
Fiscal impact
May reduce staff time/material costs to address temporary, removable graffiti.
Staff’s stated reasons
Removes undefined terms from existing ordinance language to promote clarity
Eases restrictions on most "sidewalk chalk"
Limits staff's ability to remove chalk from City-owned property or order removal from private property, which may cause an increase in visible chalk markings
Before it reached Council
Public Safety Committee, March 26, 2026: approve (2–0) — 2-0 approval to move forward to City Council
City Code sections
Sec. 10-110, §§ 10-110-10-115
From the attachments
Proposed Ordinance - Graffiti ↗: Graffiti: Writings, drawings, inscriptions, figures or marks of paint, ink, dye, sprayable chalk (including chalk paint, marking chalk, inverted chalk, and similar substances), or other similar substancesMarkings made using temporary, easily removable chalk or other water soluble markings are not included in this definition if made upon streets or sidewalks unless it is determined that such markings create a public safety risk.This definition shall not be construed to prohibit any markings used to denote the location of underground utility infrastructure and those used in conjunction with establishing survey control data and location points by survey crews.
Staff: Amy Deyton, Director; Carly Gillingham, Asst. City Attorney.
Description in the minutes
, ordinance amending Article VI, Regulation of Graffiti, of Chapter 10, Nuisances, of the Asheville Code of Ordinances, to amend the definition of graffiti, on its second and final reading. This motion was seconded by Councilman Hess and carried unanimously. VI. New Business: VII. Informal Discussion And Public Comment: Three individuals spoke to City Council about various matters, some being, but are not limited to: need for more communication between developers and neighborhoods when proposing a conditional use project; need to take a step back and look at surveillance infrastructure as a whole and invite the public to have input into the conversation; and need to increase the transit system routes and timeliness. VIII. Adjournment: Mayor Manheimer adjourned the meeting at 7:07 p.m. _______________________________ Mayor _______________________________ City Clerk 4-28-26 Page
Copied word for word from the minutes (“…” marks words left out).
Show the other 17 votes · consent agenda and routine items · consent agenda moved by Maggie Ullman, seconded by Sage Turner
Item A · Administrative · consent agenda
Approval of the combined minutes of the worksession held on April 9, 2026, and the formal meeting held on April 14, 2026
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Description in the minutes
agenda briefing worksession held on April 9, 2026, and the formal meeting held on April 14, 2026 B. Resolution Number 26-65
Resolution to permit the possession and consumption of malt beverages and/or unfortified wine at Asheville Veganfest on June 7, 2026
Resolution Number 26-66
Resolution to permit the possession and consumption of malt beverages and/or unfortified wine at the Asheville Craft Beer Half Marathon on August 29, 2026
- N. C. Gen. Stat. sec. 18B-300(c) authorizes the City by ordinance to regulate or prohibit the consumption and/or possession of open containers of malt beverages and unfortified wine on public streets and property owned, occupied, or controlled by the City and to regulate or prohibit the possession of malt beverages and unfortified wine on public streets, alleys or parking lots which are temporarily closed to regular traffic for special events.
The City Council of the City of Asheville has adopted an ordinance pursuant to that statutory authority; and that ordinance, codified as Section 11-11 in the Code of Ordinances of the City of Asheville, provides that the City Council may adopt a resolution making other provisions for the possession of malt beverages and/or unfortified wine at a special event or community festival.
Triangle Vegfest has requested that City Council permit them to serve beer and/or unfortified wine at Asheville Veganfest on June 7, 2026, at Pack Square Park, and allow for consumption at the event.
Sisu Running Foundation has requested that City Council permit them to serve beer and/or unfortified wine at the Asheville Craft Beer Half Marathon on August 29, 2026, at Pack Square Park, and allow for consumption at the event.
Alcohol boundaries are defined as per the accompanying event site maps. Approval would allow fundraising opportunities for the sponsoring nonprofit organizations. No negative fiscal impacts have been identified.
Motion to adopt resolutions to permit the possession and consumption of malt beverages and/or unfortified wine at Asheville Veganfest and the Asheville Craft Beer Half Marathon.
Copied word for word from the minutes (“…” marks words left out).
Item B · RES 26-65 / RES 26-66 · Community Programs · Resolution · consent agenda
Resolutions to permit possession and consumption of malt beverages/wine at Asheville Veganfest and the Asheville Craft Beer Half Marathon
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Key facts
Pack Square Parkaddress
Triangle Vegfest … Sisu Running Foundationapplicant
From the staff report
Adoption of resolutions to permit the possession and consumption of malt beverages and/or unfortified wine at Asheville Veganfest and at the Asheville Craft Beer Half Marathon.
Triangle Vegfest has requested that City Council permit them to serve beer and/or unfortified wine at Asheville Veganfest on June 7, 2026, at Pack Square Park, and allow for consumption at the event. Sisu Running Foundation has requested that City Council permit them to serve beer and/or unfortified wine at the Asheville Craft Beer Half Marathon on August 29, 2026, at Pack Square Park, and allow for consumption at the event.asked for this item
Fiscal impact
This action requires no City resources and has no fiscal impact.
Staff’s stated reasons
Approval would allow fundraising opportunities for the sponsoring nonprofit organizations.
No negative fiscal impacts have been identified.
City Code sections
N. C. Gen. Stat. sec. 18B-300(c), Section 11-11
Staff: Chris Corl, Director, Department of Community & Regional Entertainment Facilities; Jon Fillman, Community Event Manager.
Description in the minutes
- Resolution to permit the possession and consumption of malt beverages and/or unfortified wine at Asheville Veganfest on June 7, 2026
Resolution Number 26-66
Resolution to permit the possession and consumption of malt beverages and/or unfortified wine at the Asheville Craft Beer Half Marathon on August 29, 2026
- N. C. Gen. Stat. sec. 18B-300(c) authorizes the City by ordinance to regulate or prohibit the consumption and/or possession of open containers of malt beverages and unfortified wine on public streets and property owned, occupied, or controlled by the City and to regulate or prohibit the possession of malt beverages and unfortified wine on public streets, alleys or parking lots which are temporarily closed to regular traffic for special events.
The City Council of the City of Asheville has adopted an ordinance pursuant to that statutory authority; and that ordinance, codified as Section 11-11 in the Code of Ordinances of the City of Asheville, provides that the City Council may adopt a resolution making other provisions for the possession of malt beverages and/or unfortified wine at a special event or community festival.
Triangle Vegfest has requested that City Council permit them to serve beer and/or unfortified wine at Asheville Veganfest on June 7, 2026, at Pack Square Park, and allow for consumption at the event.
Sisu Running Foundation has requested that City Council permit them to serve beer and/or unfortified wine at the Asheville Craft Beer Half Marathon on August 29, 2026, at Pack Square Park, and allow for consumption at the event.
Alcohol boundaries are defined as per the accompanying event site maps. Approval would allow fundraising opportunities for the sponsoring nonprofit organizations. No negative fiscal impacts have been identified.
Motion to adopt resolutions to permit the possession and consumption of malt beverages and/or unfortified wine at Asheville Veganfest and the Asheville Craft Beer Half Marathon.
Copied word for word from the minutes (“…” marks words left out).
Item C · RES 26-67 · Housing · Resolution · consent agenda
Resolution authorizing an Amended Joint Cooperation Agreement adding Mars Hill and Marshall to the Asheville Regional Housing Consortium
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Key facts
Town of Mars Hill and the Town of Marshallcontractor or recipient
From the staff report
Adoption of a resolution to add the Towns of Marshall and Mars Hill to the Asheville Regional Housing Consortium
Fiscal impact
N/A
Staff’s stated reasons
Including Marshall and Mars Hill in the consortium would sustain community input and offer valuable perspectives on the diverse populations we serve.
To successfully admit Marshall and Mars Hill to the Consortium, all current members must provide a signed resolution from their respective governing boards approving the addition of the new members.
Before it reached Council
Asheville Regional Housing Consortium, August 27, 2025 (unanimously) — On August 27, 2025, the Asheville Regional Housing Consortium voted unanimously to direct the City of Asheville to effect the addition of Marshall and Mars Hill townships to the Asheville Regional Housing Consortium.
Staff: Nikki Reid, Community Development Department Director; Kaylee Pulliam, Community Development Analyst.
Description in the minutes
Resolution authorizing the City Manager to execute an Amended Joint Cooperation Agreement to add the Town of Mars Hill and the Town of Marshall to the Asheville Regional Housing Consortium
The Asheville Regional Housing Consortium has been operating under the assumption that Marshall and Mars Hill were active members; however, city staff were recently informed that the process to officially add these two new members was never finalized.
Staff is currently working with the existing consortium members to formalize the addition of the Towns of Marshall and Mars Hill.
To successfully admit Marshall and Mars Hill to the Consortium, all current members must provide a signed resolution from their respective governing boards approving the addition of the new members.
Move to approve a resolution to authorize the addition of Marshall and Mars Hill to the Asheville Regional Housing Consortium.
Copied word for word from the minutes (“…” marks words left out).
Item D · RES 26-68 · Housing · Resolution · consent agenda
Resolution authorizing an amendment to the Interlocal Agreement with Buncombe County for Code Purple emergency operations
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Key facts
$8,753.29operational costs for service providers for daytime operations February 1 and 2, 2026
$4,376.64matching County funds for Code Purple emergency operations
$50,000budgeted funds to support Code Purple
Buncombe Countycontractor or recipient
American Rescue Plan Act (ARPA) fundsfunding source
From the staff report
Adoption of a resolution authorizing the City Manager to execute an amendment to the Interlocal Agreement with Buncombe County to accept and administer matching County funds for Code Purple emergency operations
$4,376.64from Buncombe County for this purpose
$4,376.65in available American Rescue Plan Act funds to cover cost of daytime Code Purple operations on February 1 - 2, 2026
$8,753.29support operational costs for service providers for daytime operations February 1 and 2, 2026, which total $8,753.29
$50,000each provided $50,000 in budgeted funds to support Code Purple
Buncombe County, American Rescue Plan Act (ARPA)funding source
Fiscal impact
Accept $4,376.64 from Buncombe County and match with $4,376.65 in available American Rescue Plan Act funds to cover cost of daytime Code Purple operations on February 1 - 2, 2026
Staff’s stated reasons
Provide resources to make lifesaving space available during critical emergency conditions due to Winter Storm Gianna
Staff: Nikki Reid, Community and Economic Development Director; Emily Ball, Homeless Strategy Division Manager.
Description in the minutes
Resolution authorizing the City Manager to execute an amendment to the Interlocal Agreement with Buncombe County to accept and administer matching County funds for Code Purple emergency operations
The Asheville-Buncombe Continuum of Care (CoC) coordinated the plan, providers, and budgets for Code Purple and Winter Shelter this season.
The City of Asheville and Buncombe County each provided $50,000 in budgeted funds to support Code Purple. City staff administer all funds through contracts with service providers based on the CoC’s plan.
In response to Winter Storm Gianna, Code Purple providers collaborated to stay open during the day due to life-threatening temperatures.
City and County management have agreed to support operational costs for service providers for daytime operations February 1 and 2, 2026, which total $8,753.29.
Staff are seeking Council action to accept $4,376.64 from Buncombe County for this purpose. Matching City funds will be provided through available American Rescue Plan Act (ARPA) funds.
Motion authorizing a resolution authorizing the City Manager to execute an amendment to the Interlocal Agreement with Buncombe County to accept and administer matching County funds for Code Purple emergency operations
Copied word for word from the minutes (“…” marks words left out).
Item E · RES 26-69 · Utilities & Infrastructure · Resolution · consent agenda
Resolution authorizing a three year general services contract with RTI International for lead and copper testing
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Key facts
RTI Internationalcontractor or recipient
3 yearsterm
From the staff report
Adoption of resolution authorizing the City Manager to enter into a three year general services contract with RTI International for $189,956.00 to provide lead and copper analysis, and to sign any documents necessary to effect this resolution.
$189,956enter into a three year contract with RTI International
Water Resources operating budgetfunding source
Staff performed outreach through solicitation processes which include posting on the State's Interactive Purchasing SystemThe lowest, responsible bidder was RTI International, from Durham, NC, at the amount of $189,956.00.
Fiscal impact
Water Resources will enter into a three year contract with RTI International for $189,956.00 which will come from the Water Resources operating budget.
Staff’s stated reasons
Will help inform customers about potential lead in their homes.
Will help Water Resources gain a better understanding of potential areas of concern.
City Code sections
N.C.G.S. sec. 160A-312, N.C.G.S. sec. 160A-20.1
Staff: Bill Hart, Water Resources Director; Brenna Cook, Compliance Manager.
Description in the minutes
Resolution authorizing the City Manager to enter into a three year general services contract with RTI International to provide lead and copper testing
This contract is part of the City’s Free Lead Testing for all City of Asheville Water Customers to help expand the Lead Awareness Education Program.
Will help customers determine if there is a lead issue with their household plumbing or service line.
The lead and copper analysis is free for any City of Asheville Water Customer.
Will help Water Resources identify any areas where lead could be present in the service lines and prepare for the Lead and Copper Rule Improvements that come into effect November 1, 2027.
Motion to adopt a resolution authorizing the City Manager to enter into a three year general services contract with RTI International to provide lead and copper analysis of drinking water for the City’s compliance testing and Customer Lead Testing Program, and to sign any documents necessary to effect this resolution.
Copied word for word from the minutes (“…” marks words left out).
Item F · RES 26-70 · Utilities & Infrastructure · Resolution · consent agenda
Resolution authorizing an amendment to a contract with Chonzie, Inc. for predictive modeling service line inventory
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Key facts
$140,200current contract # 92600338
$8,782.04fuel surcharge
$148,982.04total contract amount will not exceed
Chonzie, Inc.contractor or recipient
From the staff report
Adoption of a resolution authorizing the City Manager to amend current contract # 92600338 with Chonzie, Inc. for predictive modeling service line inventory with the Water Resources Department from $140,200.00 to add a fuel surcharge of $8,782.04. The total contract amount will not exceed $148,982.04.
$140,200with the Water Resources Department from $140,200.00
$8,782.04fuel surcharge
$148,982.04The total contract amount will not exceed $148,982.04
Water Resources Capital Projects Fundfunding source
Informal Construction BidA search for utilities contractors was performed on the city's vendor list, NCDOT DBE list and NC HUB lists. … The Informal Construction Bid was posted on the City website and NC DOA HUB websites.
Fiscal impact
Funding for this contract was budgeted and is available in the Water Resources Capital Projects Fund.
Staff’s stated reasons
Due to a 53% increase in fuel prices since the bidding process, a fuel surcharge is being added to the contract.
The contractor will be required to provide fuel receipts to track cost during the project.
The cost of the amendment remains below the next lowest responsible bid received during the outreach process.
The inventory project will reduce the amount of unknown service line material throughout the City's water distribution system.
City Code sections
N.C.G.S. sec. 143-131, N.C.G.S. sec. 160A-312, N.C.G.S. sec. 160A-20.1
Staff: Bill Hart, Water Resources Director; Brenna Cook, Compliance Manager.
Description in the minutes
Resolution authorizing the City Manager to amend a contract Chonzie, Inc. for predictive modeling service line inventory with the Water Resources Department
Water Resources is required to build a water service line inventory per US EPA & NC Department of Environment Quality (NCDEQ) regulations.
Water Resources service line inventory currently has approximately 37,000 service lines classified as unknown sites, which must be determined by October 2027.
Water Resources is currently under contract with VODA.ai to provide predictive modeling services to help meet the service line inventory deadline requirements.
Currently the predictive modeling process requires 385 locations to be investigated to supply the predictive modeling software data to determine next steps in the inventory process.
Chonzie, Inc. was selected to perform the service line inspections required for the project after Water Resources performed the Informal Construction Bid process.
Due to a 53% increase in fuel prices since the bidding process, a fuel surcharge is being added to the contract.
The contractor will be required to provide fuel receipts to track cost during the project.
Motion to adopt a resolution authorizing the City Manager to amend current contract # 92600338 with Chonzie, Inc. for predictive modeling service line inventory with the Water Resources Department from $140,200.00 to add a fuel surcharge of $8,782.04. The total contract amount will not exceed $148,982.04.
Copied word for word from the minutes (“…” marks words left out).
Item H · RES 26-72 · Utilities & Infrastructure · Resolution · consent agenda
Resolution authorizing an amendment to the professional services contract with Ardurra Group for North Fork Transmission Main No. 3
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Key facts
$268,000City of Asheville Water Resources Department Capital Improvement Project budget
Ardurra Group, Inc.contractor or recipient
Hazard Mitigation Grant (HMGP)funding source
From the staff report
Adoption of a resolution authorizing the City Manager to amend the professional services contract with Ardurra Group, Inc. to provide engineering services for North Fork Transmission Main No 3 Project.
$268,000initially funded the contract with $268,000 from the City of Asheville Water Resources Department Capital Improvement Project budget
$5,610,850Increase the current contract value by $5,610,850
$5,878,850to a not to exceed contract value of $5,878,850
N.C. Department of Environmental Quality (DEQ) State Revolving Fund, The design and construction of this project has been submitted for a Hazard Mitigation Grant (HMGP)funding source
the City of Asheville Water Resources staff issued a RFQ to provide a competitive process for obtaining a qualified contractor to provide professional services for the North Fork Transmission Main No. 3 project · 4 responsesNo vendor outreach was performed as this is for adjustments to an existing professional services contract. … Ardurra Group, Inc. Company was one of four firms that provided proposals
Fiscal impact
Existing contract value is $268,000 Increase the current contract value by $5,610,850 to a not to exceed contract value of $5,878,850 by utilizing the recently approved funding from N.C. Department of Environmental Quality (DEQ) State Revolving Fund.
Staff’s stated reasons
This project will add a high degree of resilience and redundancy to the City of Asheville Water Distribution System.
Protects the City of Asheville and Buncombe County from prolonged water outages due to potential storm events.
The proposed project will require significant funding from Federal and State grants to complete, so there is a risk that expenditures on the project may not get reimbursed if the grant funding is not approved.
City Code sections
N.C.G.S. sec. 160A-312, N.C.G.S. sec. 160A-20.1, N.C.G. S.sec. 143-64.31
Staff: Bill Hart, Water Resources Director; Chad Pierce, Engineering Services Manager.
Description in the minutes
- Resolution authorizing the City Manager to amend the professional services contract with Ardurra Group, Inc. to provide engineering services for North Fork Transmission Main No 3 Project
- The existing professional services contract provides engineering design services for the proposed North Fork Transmission Main No 3 Project, which includes approximately 30,000 linear feet of new Water Transmission Main and all associated infrastructure and appurtenances from North Fork Water Treatment Plant.
In the aftermath of Hurricane Helene, it was determined that a new transmission main from the City’s primary water treatment plant is needed and it must be routed at a higher elevation further away from a restricted river corridor to reduce vulnerabilities to future flooding events. This proposed mitigation project is intended to meet those goals.
In August of 2025, Council authorized the City Manager to enter into a contract with the engineering consulting firm Ardurra for professional services for the North Fork Transmission Main No. 3 project.
In order to advance the contract and begin work on the preliminary design requirements, the Water Resources Department initially funded the contract with $268,000 from the City of Asheville Water Resources Department Capital Improvement Project budget, while additional funding sources were being sought.
A contract amendment is needed to increase the value of the existing professional services contract and to advance the water transmission main design to 60%.
The design and construction of this project has been submitted for a Hazard Mitigation Grant (HMGP). If awarded, the City will be reimbursed for this contract.
Motion to adopt a resolution authorizing the City Manager to amend the professional services contract with Ardurra Group, Inc. to provide engineering services for North Fork Transmission Main No 3 Project.
Copied word for word from the minutes (“…” marks words left out).
Item K · RES 26-75 / ORD 5214 · Utilities & Infrastructure · Resolution · consent agenda
Resolution authorizing a contract with TRC for stormwater infrastructure design; budget amendment
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Key facts
$224,800design and engineering services for Helene Recovery - Stormwater Repairs Professional Services - Project C
$33,72015% contingency
$258,520approval of a budget amendment
TRCcontractor or recipient
FEMA PA and Hazard Mitigation Grant Program (HMGP)funding source
From the staff report
Adoption of a resolution authorizing the City Manager to enter into a contract with TRC, in the amount of $224,800 for design and engineering services for Helene Recovery - Stormwater Repairs Professional Services - Project C, to repair or replace damaged stormwater infrastructure; and further authorizing the City Manager to execute any change orders that may arise during the project up to the 15% contingency amount of $33,720; and approval of a budget amendment of $258,520 to add federal and state funds to the Stormwater Capital Projects Fund.
$224,800in the amount of $224,800 for design and engineering services for Helene Recovery - Stormwater Repairs Professional Services - Project C
$33,72015% contingency
$258,520budget amendment
Federal Emergency Management Agency - Public Assistance (FEMA-PA) program, Federal Emergency Management Agency - Hazard Mitigation Assistance (FEMA-HMA)funding source
Request for Qualifications · 15 responsesOn December 19, 2025, staff posted a Request for Qualifications (298-FY26-PW-RFQ-Stormwater Repairs - Helene Recovery Project) for the services to design stormwater repairs. The qualifications were due January 29, 2026. Fifteen submissions were received and evaluated for each of the three projects by a four-member selection committee from the Public Works and Parks and Recreation departments. … 9 MWBE vendors were notified of the City of Asheville professional services opportunity. TRC was selected by staff as the best-qualified firm
Fiscal impact
This project is expected to be reimbursed by the Federal Emergency Management Agency - Public Assistance (FEMA-PA) program and by Federal Emergency Management Agency - Hazard Mitigation Assistance (FEMA-HMA).
Staff’s stated reasons
Repair of damaged stormwater infrastructure
Restore runoff treatment areas and improve water quality flowing to French Broad River
Construction impacts resulting in detour routes for residents, visitors, and property owners.
City Code sections
N.C.G.S. § 143-64
Staff: Amy Deyton, Director, Public Works Department; Derek Wainscott, Stormwater Division Manager, Public Works.
Description in the minutes
- Resolution authorizing the City Manager to enter into a contract with TRC for design and engineering services for one of three City-wide recovery projects to repair or replace damaged stormwater infrastructure; and further authorizing the City Manager to execute any change orders that may arise during the project up to the 15% contingency amount
Ordinance Number 5214- Budget amendment in the amount of $258,520 to add federal and state funds to the Stormwater Capital Projects Fund for the TRC Contract
- The City of Asheville has a need to hire qualified engineering professionals to help the City rebuild its infrastructure after severe damage from Tropical Storm Helene.
There are roughly fifty (50) locations in the City-wide Stormwater Repairs Helene Recovery Project where standalone stormwater infrastructure was damaged from the storm, including pipes, catch basins, junction boxes, head/end walls, inlets, and outlets.
In an effort to accelerate the project schedule, the standalone locations were separated into three design projects (Project A, B, and C).
The sites were primarily grouped geographically and by work type (e.g. stormwater control measures).
On December 19, 2025, staff posted a Request for Qualifications (298-FY26-PW-RFQ-Stormwater Repairs
Helene Recovery Project) for the services to design stormwater repairs.
The qualifications were due January 29, 2026. Fifteen submissions were received and evaluated for each of the three projects by a four-member selection committee from the Public Works and Parks and Recreation departments.
Project C is one of three contracts to repair stormwater infrastructure damages from Tropical Storm Helene. Project C includes locations along Craven Street in Asheville and includes five (5) Stormwater Control Measure sites consisting of Porous Paving, Planted Treatment Swale, Wetland system, and Bioretention.
The scope of design and engineering services encompasses:
Restoration of five (5) Stormwater Control Measures located on or near Craven Street
Analysis of the stormwater system, including, but not limited to, bioretention, porous pavers, wetlands, swales, pipe sizing and additional treatment methods for mitigation.
Repair or replacement of any related embankment, subgrade, roadway pavement, curb and gutter, concrete sidewalk, handrails, and armoring or energy dissipation which is disturbed by the pipe replacement or repair.
Recommendations on mitigation work and opportunities for resiliency.
Preparation of all necessary regulatory and environmental compliance documentation.
Final construction documents ready for bid advertising.
Funding for this project is anticipated to come from multiple sources, including FEMA PA and Hazard Mitigation Grant Program (HMGP).
The Federal Emergency Management Agency (FEMA) proposed Schedule: Design and Permitting: May 2026
February 2027 Construction Bid: March 2027
Motion to adopt a resolution authorizing the City Manager to enter into a contract with TRC, in the amount of $224,800 for design and engineering services for Helene Recovery
Stormwater Repairs Professional Services
Project C, to repair or replace damaged stormwater infrastructure; and further authorizing the City Manager to execute any change orders that may arise during the project up to the 15% contingency amount of $33,720; and approval of a budget amendment of $258,520 to add federal and state funds to the Stormwater Capital Projects Fund.
Copied word for word from the minutes (“…” marks words left out).
Item L · RES 26-76 · Transportation · Resolution · consent agenda
Resolution authorizing an application to the FHWA Emergency Relief Program and Memorandum of Agreement with NCDOT
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Key facts
N.C. Dept. of Transportationcontractor or recipient
Federal Highway Administration - Emergency Relief Program (FHWA-ER)funding source
From the staff report
Adoption of a resolution to authorize the City Manager to submit an application to the Federal Highway Administration - Emergency Relief Program (FHWA-ER) for funding of repairs on Federal-aid routes in the City of Asheville; to accept said grant funds if awarded; enter into any documents necessary for such acceptance from the FHWA-ER; and enter into a Memorandum of Agreement with the N.C. Dept. of Transportation.
$3,705,035estimated FHWA grant request
FHWA will reimburse 80% of eligible costs, 20% of the cost share to be covered by the Cityfunding source
Fiscal impact
FHWA will reimburse 80% of eligible costs with 20% of the cost share to be covered by the City. Estimated FHWA Grant request is $3,705,035
Staff’s stated reasons
FHWA-ER funding will provide permanent restoration of damaged slopes, roadways, sidewalk infrastructure as identified as Federal-aid highways.
The City is responsible for restoring and maintaining this infrastructure.
City Code sections
N.C.G.S. 160a-17.1
Staff: Amy Deyton, Public Works Director; Jaime Matthews, Deputy Recovery Coordinator.
Description in the minutes
- Resolution to authorize the City Manager to submit an application to the Federal Highway Administration
Emergency Relief Program (FHWA-ER) for funding of repairs on Federal-aid routes in the City of Asheville; to accept said grant funds if awarded; enter into any documents necessary for such acceptance from the FHWA-ER; and enter into a Memorandum of Agreement with the N.C. Dept. of Transportation
- In September 2024, the City of Asheville was severely impacted by Tropical Storm Helene, producing unprecedented impacts on the City’s infrastructure, including roadways and sidewalks.
The FHWA-ER program provides federal funding to repair Federal-aid highways and Federal lands roads damaged by natural disasters.
FHWA-ER funding will provide permanent restoration of damaged slopes, roadways, sidewalk infrastructure as identified as Federal-aid highways.
The City is responsible for restoring and maintaining this infrastructure.
Motion to adopt a resolution to authorize the City Manager to submit an application to the Federal Highway Administration
Emergency Relief Program (FHWA-ER) for funding of repairs on Federal-aid routes in the City of Asheville; to accept said grant funds if awarded; enter into any documents necessary for such acceptance from the FHWA-ER; and enter into a Memorandum of Agreement with the N.C. Dept. of Transportation.
Copied word for word from the minutes (“…” marks words left out).
Item O · RES 26-77 · Transportation · Resolution · consent agenda
Resolution authorizing a Master Contract with ECS Southeast, LLC for On-Call Industrial Hygienist Services
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Key facts
$90,000Individual supplemental agreements that exceed
ECS Southeast, LLCcontractor or recipient
initial 12-month period with the option to renew up to two additional 12-month periodsterm
From the staff report
Adoption of a resolution authorizing the City Manager to enter into a Master Contract with ECS Southeast, LLC, for On-Call Industrial Hygienist Services for an initial 12-month period with the option to renew up to two additional 12-month periods.
$300,000with a total contract amount not to exceed $300,000 over the three years
$90,000Individual supplemental agreements that exceed $90,000 will require authorization by City Council
Applicable project budgets or departmental operating budgetsfunding source
Request for Proposals · 3 responsesIn response to a Request for Proposal, the following firms submitted proposals: Terracon, of Charlotte, North Carolina, pricing is dependent on projects and needs ECS Southeast, LLC, of Asheville, North Carolina, pricing is dependent on projects and needs Atlas Technical Consultants, LLC, of Charlotte, North Carolina, pricing is dependent on projects and needs No MWBE firms submitted bids, and all work except for lab testing will be self-performed. JWJ Consulting, LLC, a MWBE firm, will perform subcontracted lab testing.
Fiscal impact
Funding for industrial hygiene services will be authorized through individual projects and contracts and funded through applicable project budgets or departmental operating budgets.
Staff’s stated reasons
Because these services conform to the same regulatory requirements at each location, and are required on an as-needed basis across multiple City facilities and projects, staff recommends establishing a Master On-Call Contract.
Provides access to specialized environmental health expertise when needed
Ensures compliance with OSHA, EPA, and other regulatory requirements
Staff: Jade Dundas, Assistant City Manager; Amanda van Roekel, City Hall Operations Manager.
Description in the minutes
- Resolution authorizing the City Manager to enter into a Master Contract with ECS Southeast, LLC, for On-Call Industrial Hygienist Services to provide professional industrial hygiene and environmental consulting services to the City of Asheville for an initial one-year term with the option to renew up to 2 additional one-year periods
- The City of Asheville manages a diverse portfolio of municipal facilities, including City Hall, public safety facilities, community centers, and administrative and operational buildings. To ensure safe working environments, support sound facility management practices, and maintain compliance with federal and state regulations, specialized environmental health expertise is periodically required to evaluate potential occupational and environmental hazards.
Industrial hygienists provide professional services related to identifying, evaluating, and controlling environmental hazards in the workplace and built environment. Typical services may include:
Asbestos inspections, sampling, and management support
Indoor air quality investigations
Hazardous materials assessments during renovation and demolition projects
Lead-based paint assessments and clearance testing
Occupational exposure monitoring
Regulatory compliance support related to OSHA, EPA, and state regulations
Technical reporting and professional consultation
Because these services conform to the same regulatory requirements at each location, and are required on an as-needed basis across multiple City facilities and projects, staff recommends establishing a Master On-Call Contract. This contracting approach allows the City to respond quickly to environmental health concerns, support construction and renovation projects, and maintain regulatory compliance. This proposed contract complies with the On-Call Contracting Guidance provided by the City’s Purchasing Department.
The multi-year contract, up to three (3) years is subject to the annual appropriation process. If the adopted budget for any given fiscal year does not include an appropriation for the service in the General Fund budget, the City shall have the right to terminate the contract.
In any authorized contracting period, individual supplemental contracts will not exceed the budget appropriation for the services within the scope of this contract.
Individual supplemental agreements that exceed $90,000 will require authorization by City Council.
Motion to adopt a resolution authorizing the City Manager to enter into a Master Contract with ECS Southeast, LLC, for On-Call Industrial Hygienist Services for an initial 12-month period with the option to renew up to two additional 12-month periods.
Copied word for word from the minutes (“…” marks words left out).
Item P · RES 26-78 · Transportation · Resolution · consent agenda
Resolution authorizing a contract with FlashParking Inc. for Parking Access Revenue Control System software and maintenance
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Key facts
$206,363total amount not to exceed
FlashParking Inc.contractor or recipient
initial term of one year, with two optional one-year renewalsterm
From the staff report
Adoption of a resolution authorizing the City Manager to execute a contract with FlashParking Inc. for Parking Access Revenue Control System software and maintenance for an initial term of one year, with two optional one-year renewals for a total amount not to exceed $206,363; and to sign any documents necessary to effect any renewals.
$206,363The total contract amount, including both renewals (if executed) is a not to exceed amount of $206,363
$65,460Year 1 cost
$68,733Option Year 2
$72,170Option Year 3
Parking Fund operating budgetfunding source
The contract for software and maintenance will be purchased via a National Purchasing Partners (NPPGov) cooperative purchase contractThe NPPGov purchasing cooperative used a competitive RFP process to select and award the contract to Flash Parking, and purchases made using a cooperative purchasing contract are exempt from the Asheville Business Inclusion (ABI) Policy.
Fiscal impact
Funding is available in the Parking Fund operating budget.
Staff’s stated reasons
FlashParking Inc. is the City's current vendor for Parking Access Revenue Control System and software used to operate and collect revenues in the City's public parking garages. The equipment was purchased in 2021 and the existing contract will expire July 1, 2026.
A new contract with the existing vendor must be executed to continue using the existing equipment, which is still functional and has not reached the end of its useful life.
- Resolution authorizing the City Manager to execute a contract with FlashParking Inc. for Parking Access Revenue Control System software and maintenance for an initial term of one year, with two optional one-year renewals; and to sign any documents necessary to effect any renewals
- FlashParking Inc. is the City’s current vendor for Parking Access Revenue Control System and software used to operate and collect revenues in the City’s public parking garages.
The equipment was purchased in 2021 and the existing contract will expire July 1, 2026.
A new contract with the existing vendor must be executed to continue using the existing equipment, which is still functional and has not reached the end of its useful life.
Motion to adopt a resolution authorizing the City Manager to execute a contract with FlashParking Inc. for Parking Access Revenue Control System software and maintenance for an initial term of one year, with two optional one-year renewals for a total amount not to exceed $206,363; and to sign any documents necessary to effect any renewals.
Copied word for word from the minutes (“…” marks words left out).
Resolution authorizing acceptance of the NCDOT Public Transit Apprenticeship Grant Program funding
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Key facts
$51,137State costs
$5,682Local costs
$52,000Total wages + benefits
North Carolina Department of Transportationcontractor or recipient
North Carolina Department of Transportation Public Transit Apprenticeship Grant Program fundingfunding source
Fiscal Year 2027term
From the staff report
Adoption of a resolution authorizing the City Manager to accept the North Carolina Department of Transportation (NCDOT) Public Transit Apprenticeship Grant Program funding in the amount of $51,137; and to authorize the City Manager to enter into an agreement with NCDOT to fund the Apprenticeship for Fiscal Year 2027 and to expend funding on the local match, not to exceed $5,682
$51,137State costs would amount to $51,137
$5,682local match, not to exceed
$56,819The total cost for the Apprentice for FY27 is $56,819
$52,000Total wages + benefits would amount to $52,000
NCDOT provides 90% of the funding for the salary and benefits of the Apprentice, the City Transit Operations Fund would provide the remaining 10%funding source
Fiscal impact
The total cost for the Apprentice for FY27 is $56,819, with the State paying $51,137 and the City paying $5,682. The grant and City's portion of the cost will be included in the Transit Fund operating budget in Fiscal Year 2027.
Staff’s stated reasons
NCDOT provides 90% of the funding for the salary and benefits of the apprentice; the City Transit Operations Fund would provide the remaining 10%.
The City has participated in this program several times over the last decade.
The apprentice is also required by the NCDOT to prepare a research report at the end of the apprenticeship.
Staff: Ashley Haire, PE, Transportation Department Director; Jessica Morriss, AICP, Assistant Transportation Department Director; Christopher Whitlock, Transit Division Manager.
Description in the minutes
- Resolution authorizing the City Manager to accept the N.C. Dept. of Transportation (NCDOT) Public Transit Apprenticeship Grant Program funding; and to authorize the City Manager to enter into an agreement with NCDOT to fund the Apprenticeship for Fiscal Year (FY) 2027 and to expend funding on the local match
- The North Carolina Department of Transportation (NCDOT) funds and manages an annual program that places recent university graduates with an interest in public transit within a city/transit agency for 1 year as a full-time, paid staff member.
NCDOT provides 90% of the funding for the salary and benefits of the apprentice; the City Transit Operations Fund would provide the remaining 10%.
State costs would amount to $51,137. Local costs would amount to $5,682. Total wages + benefits would amount to $52,000, FICA to $3,819 and travel allowance to $1,000.
The City has participated in this program several times over the last decade.
The transit apprentice would work within the Transit Division of the Transportation Department and would assist the division with ongoing work program items related to transit service.
The apprentice is also required by the NCDOT to prepare a research report at the end of the apprenticeship.
Motion to adopt a resolution authorizing the City Manager to accept the North Carolina Department of Transportation Public Transit Apprenticeship Grant Program funding in the amount of $51,137 and to authorize the City Manager to enter into an agreement with NCDOT to fund the Apprenticeship for Fiscal Year 2027 and to expend funding on the local match, not to exceed $5,682.
Copied word for word from the minutes (“…” marks words left out).
Item R · RES 26-80 / ORD 5217 · Transportation · Resolution · consent agenda
Resolution authorizing acceptance/disbursement of FTA Section 5307 JARC and 5310 grant funds; budget amendment to the Transit Services Multi-Year Fund
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Key facts
$420,732Route 170, S3, and S6 Operations
$488,946budget amendment
Buncombe County, Land of Sky Regional Council, Senior Companions - Caregiver Project and Buncombe County Agency on Agingcontractor or recipient
Fiscal Year 2025 Section 5307 Job Access Reverse Commute Program and the Fiscal Year 2025 Section 5310 Enhanced Mobility of Seniors and Individuals with Disabilities Programfunding source
From the staff report
Adoption of a resolution authorizing the City Manager to accept, expend, and disburse Federal Transit Administration Grant funds from the Fiscal Year 2025 Section 5307 Job Access Reverse Commute Program and the Fiscal Year 2025 Section 5310 Enhanced Mobility of Seniors and Individuals with Disabilities Program; authorizing the City Manager to execute all necessary agreements with the applicable transit Subrecipients for the disbursement of the approved funds; and approving a budget amendment in the amount of $488,946 to add these federal funds to the Transit Services Multi-year Fund.
$420,732Subrecipient City of Asheville under project Route 170, S3, and S6 Operations is awarded a Federal amount of $420,732
$488,946approving a budget amendment in the amount of $488,946 to add these federal funds to the Transit Services Multi-year Fund
$245,697.17Subrecipient Buncombe County under project Supplemental Elderly and Disabled Transportation Assistance Program known as SEDTAP is awarded a Federal amount of $245,697.17
$60,507.94Subrecipient Buncombe County under project RIDE voucher program is awarded a Federal amount of $60,507.94
$150,255.18Subrecipient Henderson County under project Accessible Pedestrian Signals is awarded a Federal amount of $150,255.18
$32,485.61Subrecipient Council on Aging Buncombe County under project Call - A - Ride Program is awarded Federal amount of $32,485.61
Fiscal Year 2025 Section 5307 Job Access Reverse Commute Program, Fiscal Year 2025 Section 5310 Enhanced Mobility of Seniors and Individuals with Disabilities Programfunding source
Fiscal impact
The City's required matching funds are included annually in the Transit Fund operating budget. The City's local match for FY 2025 JARC Set-Aside funding was already encumbered. … The City "passes through" funding to each subrecipient and is not responsible for their local match. The total of pass-through funding in the amount of $488,946 will be appropriated by the budget amendment in the Transit Services Multi-Year Fund.
Staff’s stated reasons
The City Attorney's Office and Purchasing Division have determined that a City Council resolution specifically authorizing the disbursement of funds to each Subrecipient, the amount being disbursed to each, and the execution of agreements, is necessary in order to provide reimbursements to Subrecipients.
Staff: Ashley Haire, Transportation Department Director; Jessica Morriss, Transportation Department Assistant Director; Christopher Whitlock, Transit Division Manager.
Description in the minutes
- Resolution authorizing the City Manager to accept, expend, and disburse Federal Transit Administration Grant funds from the Fiscal Year 2025 Section 5307 Job Access Reverse Commute Program and the Fiscal Year 2025 Section 5310 Enhanced Mobility of Seniors and Individuals with Disabilities Program; authorizing the City Manager to execute all necessary agreements with the applicable transit Subrecipients for the disbursement of the approved funds -
Copied word for word from the minutes (“…” marks words left out).
Item S · RES 26-81 · Transportation · Resolution · consent agenda
Resolution ratifying the City's February 2026 application to NCDOT for Section 5303 Metropolitan Planning Program funding for FY2027
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Key facts
$189,839total grant
$151,871Federal Transit Administration grant will provide 80% of the anticipated funding
$18,984each providing half of the required 20% match
$18,984each providing half of the required 20% match
North Carolina Department of Transportation - Integrated Mobility Divisioncontractor or recipient
Section 5303 Metropolitan Planning Program annual fundingfunding source
Fiscal Year 2027term
From the staff report
Adoption of a resolution ratifying the City's February 2026 application to the North Carolina Department of Transportation - Integrated Mobility Division for Section 5303 Metropolitan Planning Program annual funding for Fiscal Year 2027; and authorizing the City Manager to accept any funds awarded and to enter into any agreements necessary for acceptance and expenditure of grant funds.
$189,839total grant
$151,871The Federal Transit Administration will provide 80% of the anticipated funding ($151,871)
$18,984North Carolina Department of Transportation and the City of Asheville each providing half of the required 20% match, or $18,984 each
$18,984North Carolina Department of Transportation and the City of Asheville each providing half of the required 20% match, or $18,984 each
The Federal Transit Administration will provide 80% of the anticipated funding, the North Carolina Department of Transportation and the City of Asheville each providing half of the required 20% matchfunding source
Fiscal impact
The total grant is $189,839 and includes a 20% match. The Federal Transit Administration will provide 80% of the anticipated funding ($151,871), with the North Carolina Department of Transportation and the City of Asheville each providing half of the required 20% match, or $18,984 each. This funding and match will be included in the FY 2027 Adopted Budget.
Staff’s stated reasons
The City must apply annually to the North Carolina Department of Transportation - Integrated Mobility Division to receive Federal Transit Administration Section 5303 funds (Metropolitan Planning Program). Staff applied for this funding February 16, 2026.
The funds supplement the Transit Division personnel budget, which includes the Transit Division Manager and additional transit planning staff positions.
- Resolution ratifying the City’s February 2026 Application to the North Carolina Department of Transportation
Integrated Mobility Division for Section 5303 Metropolitan Planning Program annual funding for Fiscal Year 2027
- The City must apply annually to the North Carolina Department of Transportation
Integrated Mobility Division to receive Federal Transit Administration Section 5303 funds (Metropolitan Planning Program). Staff applied for this funding February 16, 2026.
The City uses the Federal Transit Administration Section 5303 funding to fund existing transit planning activities such as grant management, administration, and reporting; short- and long-range transit planning; analyses of transit operations; and required program preparation and reporting.
The funds supplement the Transit Division personnel budget, which includes the Transit Division Manager and additional transit planning staff positions.
The total grant is $189,839 and includes a 20% match. The Federal Transit Administration grant will provide 80% of the anticipated funding ($151,871), with the North Carolina Department of Transportation and the City of Asheville each providing half of the required 20% match, or $18,984 and $18,984, respectively.
Motion to adopt a resolution ratifying the City’s February 2026 application to the North Carolina Department of Transportation
Integrated Mobility Division for Section 5303 Metropolitan Planning Program annual funding for Fiscal Year 2027; and authorizing the City Manager to accept any funds awarded and to enter into any agreements necessary for acceptance and expenditure of grant funds.
Copied word for word from the minutes (“…” marks words left out).
Item T · RES 26-82 · Housing · Resolution · consent agenda
Resolution of the Housing Authority approving issuance of up to $18,020,000 Multifamily Housing Revenue Bonds for Pine Lane Apartments
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
Key facts
$18.02 millionMultifamily Housing Revenue Bonds
36 Pine Laneaddress
9.42 acressite size
126 units126 of them affordable
All units will be set aside for individuals and families at 60% or less of Area Median Income (“AMI”). … The affordability period will be 30 years.affordability
Roers Asheville Apartments Owner LLCapplicant
Housing Authority of the City of Ashevillecontractor or recipient
Multifamily Housing Revenue Bondsfunding source
From the staff report
Adoption of a resolution approving the issuance of bonds by the Housing Authority of the City of Asheville for Pine Lane Apartments
Roers Asheville Apartments Owner LLC, a North Carolina limited liability company, or an affiliated or related entity (the "Borrower") has requested that the Asheville Housing Authority (the "Issuer") issue up to $18,020,000 in multifamily housing revenue bondsasked for this item
$18.02 millionissue up to $18,020,000 in multifamily housing revenue bonds
multifamily housing revenue bondsfunding source
9.42 acres36 Pine Lane
Roers Asheville Apartments Owner LLC, a North Carolina limited liability company, or an affiliated or related entity (the "Borrower")applicant
9627805971parcel ID (PIN)
Fiscal impact
This action requires no City resources and has no fiscal impact.
Staff’s stated reasons
The Internal Revenue Service requires that any bonds issued by the Housing Authority for developments such as the one described herein, have the financing plan approved by the City Council, following a public hearing with respect to such a plan.
Staff notes that approval does not obligate the City in any way to issue or pay for the bonds, or for any debt taken on by the developer.
Before it reached Council
Housing Authority of the City of Asheville, April 6, 2026 — on April 6, 2026, the Issuer held a public hearing with respect to the issuance of the Bonds to finance, in part, the Development
Staff: Nikki Reid, Community and Economic Development Director; Jannice Ashley, Deputy City Attorney; Carly Gillingham, Assistant City Attorney.
Description in the minutes
- Resolution of the Housing Authority of the City of Asheville to adopt a resolution approving the issuance of up to $18,020,000 Multifamily Housing Revenue Bonds to provide financing for Pine Lane Apartments to satisfy Section 147(f) of the Internal Revenue Code, with no City financial obligation associated with the bonds or any debt taken on by the developer
- The Asheville Housing Authority was created by the City of Asheville in 1940 in accordance with Chapter 157 of the NC General Statutes.
It is a public body and is independent from the City with its own powers as outlined in North Carolina General Statute Chapter 157.
The Housing Authority is governed by a Board of Commissioners, consisting of 7 members, who serve for a 4 year term and are appointed by the Mayor of the City of Asheville.
The Internal Revenue Service requires that any bonds issued by the Housing Authority for developments such as the one described herein, have the financing plan approved by the City Council, following a public hearing with respect to such a plan.
Roers Asheville Apartments Owner LLC, a North Carolina limited liability company, or an affiliated or related entity (the “Borrower”) has requested that the Asheville Housing Authority (the “Issuer”) issue up to $18,020,000 in multifamily housing revenue bonds for the acquisition and construction of a new 126-unit affordable rental development known as Pine Lane Apartments located on a 9.42 acre site at 36 Pine Lane, in the City of Asheville parcel identified as PIN 9627805971 in the Buncombe County Registry.
The project will consist of 4 residential buildings. There will be a mix of 1,2, 3 and 4-bedroom units. All units will be set aside for individuals and families at 60% or less of Area Median Income (“AMI”).
The affordability period will be 30 years.
Roers Companies is the developer of this project and is an affiliate of the owner.
Construction is scheduled to commence in July 2026 and has an expected completion date of March 28.
Staff notes that approval does not obligate the City in any way to issue or pay for the bonds, or for any debt taken on by the developer.
Motion to adopt a resolution approving the issuance by the Housing Authority of the City of Asheville of up to $18,020,000 of multifamily housing revenue bonds to provide financing for Rocky River Apartments and to satisfy Section 147(f) of the Internal Revenue Code. U. Resolution Number. 26-83
Resolution reappointing Carol Goins as Chair of the Civil Service Board -
Copied word for word from the minutes (“…” marks words left out).
Item U · RES 26-83 · Boards & Appointments · Appointment · consent agenda
Resolution reappointing Carol Goins as Chair of the Civil Service Board
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
From the staff report
Carol Goins is hereby reappointed as Chair of the Civil Service Board to serve at the pleasure of City Council, or until a successor has been appointed or unless modified by Council action.
Description in the minutes
- Resolution reappointing Carol Goins as Chair of the Civil Service Board -
Copied word for word from the minutes (“…” marks words left out).
Item V · RES 26-84 · Community Programs · Resolution · consent agenda
Resolution asking HCA Healthcare CEO Sam Hazen to engage directly with stakeholders in Western North Carolina
Passed7–0 · Moved by Maggie Ullman, seconded by Sage Turner
All members present voted yes.
From the staff report
The Asheville City Council calls on Mr. Sam Hazen, as the leader of HCA, to come to Western North Carolina and meet with elected officials, healthcare advocates, and other community leaders, be accountable for HCA's decisions at Mission Health, and engage in a collaborative and transparent dialogue to develop a plan for long term, permanent improvement at Mission Hospital and throughout the Mission Health system.
Description in the minutes
- Resolution asking HCA Healthcare Chief Executive Officer Sam Hazen to Engage Directly with Stakeholders in Western North Carolina -
Copied word for word from the minutes (“…” marks words left out).
Ms. Ball responded to various questions/comments from Council, some being, but are not limited to: explained the design of Code Purple; suggestion that shelters should be open every time there is a point-in-time count
The Continuum of Care (CoC)’s 2026 Point-in-Time Count identified a slight increase in homelessness, with results demonstrating continued impact from Helene … This year’s count occurred February 10, 2026, with 137 volunteers participating … Lack of affordable housing is the determining factor for rates of homelessness
Presented by Emily Ball, Homeless Strategy Division Manager.
Mayor Manheimer read a statement regarding Chamber decorum.
Presented by Esther E. Manheimer, Mayor.
Proclamation
National Police Week
Councilman Hess read the proclamation proclaiming May 10-16, 2026, as "National Police Week” and May 15, 2026, as “Peace Officers’ Memorial Day " in the City of Asheville. He presented the proclamation to Interim Police Chief Jackie Stepp and Deputy Police Chief Sean Aardema, and several Police Officers.
Presented by Jackie Stepp, Interim Police Chief; Sean Aardema, Deputy Police Chief.
Proclamation
Public Service Appreciation Week
Councilwoman Ullman read the proclamation proclaiming May 3-9, 2026 as “Public Service Appreciation Week in the City of Asheville. She presented the proclamation to Human Resources Manager Lauren Abe, and a cross section of other City employees from various departments.
Presented by Lauren Abe, Human Resources Manager.
Proclamation
Huntington’s Disease Awareness Month
Vice-Mayor Mosley read the proclamation proclaiming May 2026 as “Huntington’s Disease Awareness Month” in the City of Asheville. She presented the proclamation to McKenzie Luxmore, board member for HD Reach, who thanked City Council for this recognition.
Presented by McKenzie Luxmore, board member for HD Reach.
Mayor Manheimer read the proclamation proclaiming May 2026 as “Amyotrophic Lateral Sclerosis (ALS) Awareness Month” in the City of Asheville. She presented the proclamation to Margaret Black, ALS United Board Member, who briefed City Council on some activities taking place during the month.
Presented by Margaret Black, ALS United Board Member.
Open public comment 3 speakers · 3 topics, as the minutes list them
need for more communication between developers and neighborhoods when proposing a conditional use project
need to take a step back and look at surveillance infrastructure as a whole and invite the public to have input into the conversation
need to increase the transit system routes and timeliness
What staff answered afterwards 8 questions from council, answered in the city’s follow-up memos
Kim Roneymeeting, Apr 28, 2026 PFI- Item #3
How does Amazon Web Services fit into the Axon network, and how is it used for Real-Time?
Staff:Axon representative shared that she would reach out to the engineers to get clarity on this question.
Answered by APD
Kim Roneymeeting, Apr 28, 2026 PFI- Item #3
Request to review the contracts for Axon and Flock
Staff:Links to the requested agreements are included below. Please also see this memo for an explanation of the license granted to Flock in its contract with the City. Flock Agreement Axon Agreement The access to Respond/Fusus currently available to APD is included in the basic service package with Axon camera products. As of today, the City does not have a specific agreement for Fusus. The product that is in use is limited to only allowing access to Axon products, such as Body-worn and fleet cameras.
Staff:CDBG-DR Planning project one-pagers provide additional information on scope and outcomes for each project. Staff will present on the Economic Development Strategic Action Plan and the Emergency Shelter Development Plan at the PEDE meeting on May 11th. Staff will move forward with awards for Comp Plan & UDO Update and Deaverview Master Development Plan. Please contact Manager Wesley directly if you have questions about either of these two.
What are the ongoing costs and additional features between the free version and the paid version of the Fusus software?
Staff:The current version enables access to Axon devices such as body-worn and in-car cameras. The full version of Fusus provides the ability to connect non-Axon cameras, which is important for the operation of a Real Time Intelligence Center. This grant will fund Fusus for approximately 8 years at a cost of $467,602.
Sheneika Smithagenda briefing, Apr 23, 2026 Other Items/Updates City Property Review
8 River Arts Place - requests an update
Staff:The lease is currently paused. City staff is in the process of scheduling a meeting with Black Wall Street to provide an update on building condition, timeline, and options. Staff will provide Council with subsequent updates over the next few months
Answered by CED
Maggie Ullmanagenda briefing, Apr 23, 2026 Other Items/Updates City Property Review
Requests the surplus property list and a timeline of progress on 5 properties discussed (comment by DK)
Staff:Staff is working to update the City property inventory map and will share when it is available. While timelines are variable for each project, here is a list of recent/upcoming milestones for the 5 properties discussed are as follows: Parkside - Approval of 2-year land hold on March 24. ART Place - Statements of Qualifications were due on April 10. Deaverview Master Plan - Council will review allocation of CDBG-DR funds for planning at PFI on April 28. Once a planning firm is selected, the master plan process is expected to take 18 months. 300 Merrimon - following the agenda briefing, staff will conduct a kickoff with the Preservation Society to outline steps in the process, with targets for completion. 91 Riverside - following the agenda briefing, staff will finalize the draft Request for Proposals with the intent to publish in May or June, with the goal to bring recommendations to Council in late summer / early fall.
Answered by CED
Work session, Thursday, Apr 23, 2026 the agenda briefing before this meeting · 11 am–11:49 am · no votes
Other business
Agenda Briefing Worksession
City Council held an agenda briefing worksession to discuss the upcoming and future agenda items. In addition, City Council reviewed upcoming City Council committees that will be taking place during the next two weeks.
Staff briefed on
City property review
This resource, to the best of its ability, is copied word for word from the official minutes, “…” marks words left out, and [brackets] a name the minutes give elsewhere. The minutes are the record. Staff answers are quoted from the city’s follow-up memos. Staff report details are quoted from the city’s meeting documents, prepared before the vote.