Resolution authorizing the City Manager to execute contract amendments with WeaverCooke Construction for the City Hall Elevator Modernization project
Asheville City Council took this up at 3 meetings, from August 25, 2020 to June 14, 2022: 3 roll calls over 3 meetings. Most recent decision: June 14, 2022, passed 7–0.
Aug 25, 2020 · Regular meeting · Item II-H · RES 20-139
From the minutes: On August 25, 2020, City Council authorized the City Manager to enter into a Design-Build contract with Weaver Cooke Construction and to execute any associated cost amendments up to a total of $2,304,831.00.
$2.36 millionrevised total of $2,360,000.00
$2,304,831execute any associated cost amendments up to a total of $2,304,831.00
All members present voted yes.
Jun 14, 2022 · Regular meeting · Item II-E · RES 22-119 · Most recent
From the minutes: On August 25, 2020, the City Council authorized the City Manager to enter into a Design-Build contract with Weaver Cooke Construction and to execute any associated cost amendments up to a total of $2,304,831.00.
$2.49 millionrevised total of $2,490,000.00
$130,000additional $130,000.00
All members present voted yes.
Each figure is the one printed with that meeting’s item. They are not added together.